Test your project management skills10 questions

Quick 10

Ten questions at random, spread by the domain weights - four, two, two, two. Every visit to the page draws a new set.

The questions are in English, as the exam is. Every question has a Macedonian explanation beneath it, opened on a click. This page is also a study sheet: even without JavaScript every question has its answer and explanation under “Check the answer”.

Progress

Question 1 of 10

Fundamentals · Task 1easyone answer
Question 1. A bank places three related projects under one manager because coordinating them delivers benefits that none of them would deliver on its own. What is this grouping called?

Pick one answer, then check.

Check the answer

Correct answer

  • AA program
Next question

The words that decide it are related and benefits from coordination. A program exists to obtain those benefits; a portfolio exists to choose and balance investments against strategy, whether or not its components are related. A candidate who chose B saw a grouping and reached for the widest term without checking the reason for the grouping.

Why, option by option - Question 1

  • A. A program is a group of related projects and activities managed in a coordinated way to obtain benefits not available from managing them individually, which is exactly the reason given in the stem.

  • B. A portfolio groups projects, programs and operations to meet strategic objectives; its components need not be related to one another, and the grouping is about investment choice rather than coordinated benefits.

  • C. A subproject is a smaller, more manageable piece of a single project, not a grouping of several projects.

  • D. A phase is a collection of logically related activities within one project's life cycle, not a way of grouping separate projects.

Објаснување на македонски (explanation in Macedonian)

Програма е група поврзани проекти што се управуваат координирано за да се добијат придобивки што не би се постигнале поединечно. Портфолиото ги групира проектите и програмите според стратешките цели и тие не мора да бидат меѓусебно поврзани. Потпроектот и фазата се делови на еден проект.

Where this sits in PMI

PMBOK Guide 7th ed., The Standard for Project Management, section on the system for value delivery; Process Groups: A Practice Guide, introduction, relationship between portfolios, programs and projects

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0002)

Question 2 of 10

Fundamentals · Task 1mediumone answer
Question 2. A municipality's park-renovation plan treats the council's confirmation of the budget before the planting season as certain, although the vote has not been held. The contractor must finish before the first frost, and last week a delivery of paving stones arrived damaged. How should the plan's reliance on the budget vote be recorded?

Pick one answer, then check.

Check the answer

Correct answer

  • DAs an assumption, because the plan treats an unconfirmed event as true
Next question

The four terms are separated by time and certainty. The frost date is a constraint (a fixed limit), the damaged delivery is an issue (it has happened), the vote failing would be a risk (it may happen), and the plan's reliance on the vote passing is an assumption (treated as true without proof). A candidate who chose B was not wrong that a risk exists; the risk is the consequence of the assumption, and the stem asks about the assumption.

Why, option by option - Question 2

  • A. An issue is a condition that has already happened and needs resolution, such as the damaged paving stones. The vote has neither passed nor failed, so nothing has occurred yet.

  • B. A refusal is indeed a risk that flows from this planning basis, and it belongs in the risk register. But the stem asks how the basis itself is recorded, and a factor the plan treats as true without proof is an assumption from which the risk is then derived.

  • C. A constraint is a fixed limit imposed on the project, like finishing before the frost. An amount that has not been confirmed cannot yet act as a limit.

  • D. An assumption is a factor considered true, real or certain for planning purposes without proof. The plan is built on the vote passing in time, which is exactly that.

Објаснување на македонски (explanation in Macedonian)

Претпоставка е фактор што планот го смета за точен без доказ, како гласањето за буџетот што уште не е одржано. Ризик е тоа што советот би можел да одбие, ограничување е рокот пред мразот, а оштетените плочки се issue што веќе се случил. Претпоставката е основата, а ризикот произлегува од неа.

Where this sits in PMI

PMBOK Guide 7th ed., Models, methods and artifacts, logs and registers; Process Groups: A Practice Guide, planning process group, assumption log and risk register

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0003)

Question 3 of 10

Fundamentals · Task 1mediumone answer
Question 3. On a road-construction project the project manager has confirmed that a subcontractor altered material test results before submitting them to the client. The sponsor asks the project manager to leave this out of the next status report because a payment milestone depends on it. What should the project manager do?

Pick one answer, then check.

Check the answer

Correct answer

  • BReport the finding accurately through the project's agreed channels and tell the sponsor beforehand that this is what will happen
Next question

The Code of Ethics asks for honesty (accurate, timely information), responsibility (reporting unethical conduct) and respect (dealing directly with the person concerned). Option B satisfies all three and stays within the agreed governance. C is honest with one party and misleading with the rest; D jumps to the strongest external escalation before the project's own process has been given a chance. A candidate who chose D mistook the seriousness of the finding for a licence to skip the sequence.

Why, option by option - Question 3

  • A. The sponsor's authority does not extend to asking for a misleading report. The Code of Ethics places honesty above a superior's instruction, and a private note does not make an incomplete report accurate.

  • B. Honesty and responsibility require accurate reporting of material facts, and respect requires the sponsor to hear it directly rather than be surprised. This keeps both the information and the relationship intact and stays inside the project's governance.

  • C. This avoids one falsehood by creating a back channel. It still produces a status report the project manager knows to be incomplete and steps outside the project's agreed reporting path.

  • D. Stopping work and going to the client's lawyers are escalations the project manager has not yet earned by following the project's own process. The finding must be reported and dealt with first; legal escalation may follow if governance fails.

Објаснување на македонски (explanation in Macedonian)

Code of Ethics бара точно и навремено известување, одговорност да се пријави неетичко однесување и почит кон луѓето со кои се работи. Проектниот менаџер ја пријавува измената точно преку договорените канали и претходно му кажува на спонзорот. Опцијата C прикрива од едни, а открива на други; опцијата D ескалира надвор од проектот пред да се испочитува процесот.

Where this sits in PMI

PMI Code of Ethics and Professional Conduct, honesty, responsibility and respect sections; PMBOK Guide 7th ed., principles, being a diligent, respectful and caring steward

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0004)

Question 4 of 10

Fundamentals · Task 1mediummultiple answers
Question 4. A hospital is about to start work on a patient-scheduling application and is choosing between a predictive and an adaptive development approach. Which two characteristics of the work make an adaptive approach the better fit? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • BClinic staff can only say what they need after trying early working versions
  • EThe hospital wants small usable pieces released to wards every few weeks and adjusted from feedback
Next question

The suitability of an adaptive approach rises with uncertainty in requirements and with the value of frequent delivery and feedback. B (requirements emerge from use) and E (frequent usable releases adjusted from feedback) are both of that kind. A, C and D each describe stability or certainty, which makes a predictive approach the natural fit. A candidate who keyed A may have read a regulator as a sign of complexity; it is a sign of fixed scope.

Why, option by option - Question 4

  • A. Fixed, externally approved acceptance criteria are a stability signal; they favour defining the scope up front and building to it, a predictive trait.

  • B. Requirements that emerge from use rather than from analysis are the classic reason to choose an adaptive approach, which exists to discover scope through short cycles and feedback.

  • C. A fully specified scope under a fixed price is the strongest argument for a predictive approach, where the plan is baselined and changes are controlled formally.

  • D. Well-understood technology lowers uncertainty, which reduces the need for the experimentation that an adaptive approach provides.

  • E. Frequent incremental delivery with adjustment from feedback is the delivery cadence adaptive approaches are built around.

Објаснување на македонски (explanation in Macedonian)

Агилен, односно адаптивен пристап е најсоодветен кога барањата се откриваат преку употреба (B) и кога се сака честа испорака на мали употребливи делови со прилагодување според повратните информации (E). Фиксни критериуми за прифаќање, целосно дефиниран опсег со фиксна цена и добро позната технологија се знаци на стабилност што одат во прилог на предвидлив пристап.

Where this sits in PMI

Agile Practice Guide, life cycle selection and the suitability filter; PMBOK Guide 7th ed., Development approach and life cycle performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0005)

Question 5 of 10

Predictive · Task 2easyone answer
Question 5. While reviewing the work breakdown structure of a store-refit project for a retail chain, the sponsor notices that the work packages under the "Fixtures" element add up to less than all the fixture work the contract requires. Which WBS principle has been broken?

Pick one answer, then check.

Check the answer

Correct answer

  • CThe 100 percent rule
Next question

A WBS is a hierarchical decomposition of the total scope of work, and its defining principle is the 100 percent rule: each level of decomposition must contain all, and only, the work of the level above it. When the work packages under an element sum to less than the element, scope is missing from the WBS and will be missing from the schedule and budget derived from it. Rolling wave and progressive elaboration explain how detail grows; the 8/80 rule concerns work-package size.

Why, option by option - Question 5

  • A. Rolling wave planning details near-term work and leaves later work at a higher level. It is allowed in a WBS, but even a high-level element must still represent all of the work below it.

  • B. Progressive elaboration is the refining of the plan as more becomes known. It describes how detail grows over time, not whether the children of an element cover everything the parent contains.

  • C. The 100 percent rule says the WBS includes all of the project's work and that the children of any element together represent 100 percent of that element, no more and no less. Work packages that add up to less than their parent break it.

  • D. The 8/80 rule is a sizing heuristic that keeps a work package between roughly 8 and 80 hours of effort. It is about the size of a package, not about whether the packages together cover the parent.

Објаснување на македонски (explanation in Macedonian)

Структурата за поделба на работата мора да го содржи целиот опсег: работните пакети под еден елемент заедно претставуваат 100 % од тој елемент, ни повеќе ни помалку. Тоа е правилото „100 %“ (100 percent rule). Rolling wave planning и progressive elaboration опишуваат како расте деталноста, а правилото 8/80 се однесува на големината на работниот пакет.

Where this sits in PMI

Process Groups: A Practice Guide, Create WBS (decomposition and the 100 percent rule); PMBOK Guide 7th ed., Planning performance domain (scope and work breakdown structure)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0028)

Question 6 of 10

Predictive · Task 2mediumone answer
Question 6. On a predictive software project for an insurance firm, a billing module has failed its inspection. The quality management plan says defects found in inspection are repaired and re-inspected before acceptance; the repair will push the module's milestone beyond the date in the schedule baseline, and the slip cannot be recovered. The change management plan says that any change to a baseline must be formally approved before it takes effect. What should the project manager do?

Pick one answer, then check.

Check the answer

Correct answer

  • DRepair the module and re-inspect it, and submit a change request for the schedule baseline to the change control board
Next question

The project management plan is followed as agreed. The quality management plan settles what happens to a failed deliverable, so it is repaired and re-inspected. The knock-on effect on the schedule baseline is a change, and changes to baselines go through integrated change control as the change management plan requires. Option A does the first half and then bypasses change control; option B trades the plan for a date by accepting defective work, and option C treats a baseline change as an issue to be logged instead of a change to be approved.

Why, option by option - Question 6

  • A. Following the quality plan is right, but a baseline is only changed through the change control process. The project manager cannot re-baseline the schedule on their own authority, even to record a delay that is certain.

  • B. This protects the date by abandoning the quality management plan. The plan states that inspection defects are repaired before acceptance, and acceptance of known-defective work is not a decision the project manager can make alone.

  • C. Following the quality plan is right, and logging the slip is harmless, but the issue log does not authorise a change to a baseline. Only an approved change request moves the schedule baseline.

  • D. Both plans are followed as written: the quality plan decides what happens to the defective deliverable, and the change management plan decides how the resulting baseline change is handled. The board, not the project manager, approves the new baseline.

Објаснување на македонски (explanation in Macedonian)

Проект менаџмент планот се следи како што е договорен. Планот за квалитет вели дека испораката што паднала на испитување се поправа и повторно се испитува, а промената на основната линија на временскиот распоред што следува од тоа оди преку контрола на промени до одборот. Проектниот менаџер не смее сам да ја промени основната линија, ниту да прифати дефектна испорака за да ја одржи одредницата.

Where this sits in PMI

Process Groups: A Practice Guide, Control Quality and Perform Integrated Change Control; PMBOK Guide 7th ed., Delivery performance domain (quality) and Planning performance domain (baselines and change)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0029)

Question 7 of 10

Agile · Task 1mediumone answer
Question 7. A logistics company is about to run its first adaptive project, with the team split between two offices. Before work starts, the project manager reviews the enterprise environmental factors and organisational process assets. Which condition would most facilitate the adaptive approach?

Pick one answer, then check.

Check the answer

Correct answer

  • AA product owner from the business who is available to the team throughout each iteration
Next question

The environmental factors and process assets that help an adaptive approach are those that speed up feedback and decisions: an engaged, available product owner, dedicated cross-functional team members, collaboration tooling for distributed teams and a culture that accepts change. Option A is the only condition that supplies them. Option C looks similar but the feedback cadence is wrong, option B describes a role acting against agile principles and option D belongs to the predictive toolbox.

Why, option by option - Question 7

  • A. Adaptive approaches depend on rapid decisions about value and priority. A product owner who is present every day answers questions, accepts work and reorders the backlog without waiting for a committee, and for a team split between offices that presence matters even more.

  • B. The scrum master is a servant leader who removes impediments and coaches the team; work is pulled by self-organising team members, not assigned. A scrum master who assigns work undermines the self-organisation the approach relies on.

  • C. A product owner exists, but quarterly feedback defeats the point of short iterations: the team would build for months without knowing whether the increment is right. Feedback has to arrive at least once per iteration.

  • D. These are organisational process assets that support a predictive life cycle. Phase gates and detailed schedule templates add ceremony an adaptive team does not use, so they do not facilitate the approach.

Објаснување на македонски (explanation in Macedonian)

Адаптивниот пристап најмногу го олеснува Сопственик на продуктот кој е достапен за тимот во текот на секоја итерација, зашто тој брзо одлучува за вредноста и приоритетите. Scrum Мастер не доделува задачи (опција B), квартална повратна информација е премногу ретка (опција C), а шаблоните и фазните контроли се средства за предиктивен пристап (опција D).

Where this sits in PMI

Agile Practice Guide, section 4.3 (team composition and agile roles) and section 6.2 (organisational culture); PMBOK Guide 7th ed., Team performance domain and Development Approach and Life Cycle performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0034)

Question 8 of 10

Agile · Task 2easyone answer
Question 8. A software team at a retail chain is planning its next two-week sprint. The product owner proposes the single objective the sprint should achieve, and the team then selects the backlog items that support it. What is this objective called?

Pick one answer, then check.

Check the answer

Correct answer

  • DSprint goal
Next question

In sprint planning the product owner proposes why the sprint is valuable, the team turns that into a sprint goal and then selects backlog items to deliver it. The product goal is the longer horizon, the sprint backlog is the output of the selection and the definition of done is the quality bar; only the sprint goal is the objective of the timebox.

Why, option by option - Question 8

  • A. The product goal is the longer-term objective the whole product backlog works toward, spanning many sprints. The objective proposed for one sprint is a step toward it, not the goal itself.

  • B. The sprint backlog is the set of items the team selects plus its plan for delivering them. It is built to serve the objective; it is not the objective.

  • C. The definition of done states the quality conditions every item must meet before it counts as complete. It applies to all sprints and does not describe what one particular sprint sets out to achieve.

  • D. The sprint goal is the one objective the sprint commits to, agreed in sprint planning. It gives the team a shared purpose and guides which items are selected and how scope is negotiated during the sprint.

Објаснување на македонски (explanation in Macedonian)

Целта што Сопственикот на продуктот ја предлага за еден Спринт, а тимот ја усвојува во Планирање на Спринтот, е Цел на Спринтот. Цел на Продуктот е долгорочна и опфаќа многу спринтови, Листа на планирани активности за Спринтот се избраните ставки, а Дефиниција за Завршено е условот за квалитет на секоја ставка.

Where this sits in PMI

Agile Practice Guide, section 5.2.6 (planning for iteration-based agile) and Annex A3 (Scrum); PMBOK Guide 7th ed., Planning performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0035)

Question 9 of 10

Business analysis · Task 3easyone answer
Question 9. The logistics team of a humanitarian NGO wants to see how a donated shipment moves from arrival at the warehouse to distribution in the field, including every hand-off between departments, so that the delays can be found. Which requirements tool fits this need best?

Pick one answer, then check.

Check the answer

Correct answer

  • BA process model
Next question

Matching a tool to the scenario: an end-to-end flow with hand-offs and waiting points is what a process model is built to show. User stories and use cases describe needs and system interactions, and a prototype shows a future solution. A candidate who chose the use case confused a single actor's interaction with a system for a cross-departmental flow of work.

Why, option by option - Question 9

  • A. A user story captures a single need from one role's point of view in a sentence or two. It is deliberately small and does not show a sequence of hand-offs across departments.

  • B. A process model (a flow diagram with swimlanes) shows the steps, decisions and hand-offs between roles from the start of a process to its end. It is the tool for seeing where work waits, which is exactly what the team wants.

  • C. A use case describes how an actor interacts with a system to reach a goal, step by step. It centres on one interaction with the solution, not on how work flows between several departments.

  • D. A prototype makes a proposed solution tangible so stakeholders can react to it. The team is trying to understand the current process, not to try out a future screen or product.

Објаснување на македонски (explanation in Macedonian)

Тек на работа од почеток до крај, со предавања меѓу одделенијата, најдобро се прикажува со process model. User story опишува една потреба на една улога, use case опишува како актер комуницира со системот, а прототип прикажува идно решение, не постоечки процес.

Where this sits in PMI

PMI Guide to Business Analysis, Analysis knowledge area (process models, use cases, user stories); Business Analysis for Practitioners: A Practice Guide, 2nd ed., analysis chapter (modelling techniques)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0050)

Question 10 of 10

Business analysis · Task 3mediummultiple answers
Question 10. An insurance company is replacing a claims system used by nine hundred clerks in forty branches. Within a month the business analyst must learn how the clerks actually handle a claim today and how widely a proposed change to the approval step would be accepted across the branches. Which two elicitation techniques best fit this situation? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • AObserving clerks handling claims at a sample of branches
  • DSurveying the clerks in all forty branches

Two questions, two techniques: observation for how the work is actually done (people cannot reliably describe their own habits) and a survey for a broad, dispersed population whose acceptance must be measured in a short time. The other options use legitimate techniques with the wrong participants, which is the trap: the technique is only as good as who it is applied to. A candidate who chose the sponsor interview mistook the sponsor's authority for knowledge of branch practice.

Why, option by option - Question 10

  • A. Observation shows what people actually do, including the workarounds they would not think to describe. It is the technique for learning how a process really runs today, and a sample of branches makes it feasible within the month.

  • B. An interview is right for depth with one person, but the sponsor is not the one performing the work and cannot say how forty branches would receive the change. It answers neither of the two questions the analyst has.

  • C. Brainstorming generates ideas for how something could be done; it does not produce evidence of how nine hundred clerks handle a claim today, and a single head-office group cannot show how forty branches would receive the change.

  • D. A survey reaches a large, dispersed population quickly and gives a measurable picture of how a proposed change is received. For nine hundred people in forty locations within a month, it is the technique that scales.

  • E. A focus group gathers the views of a selected group of stakeholders, but the developers neither perform the claims process nor decide whether the approval change is acceptable in the branches. The wrong participants make the technique miss the target.

Објаснување на македонски (explanation in Macedonian)

Две прашања бараат две техники: набљудување на службениците за да се види како навистина работат, и анкета за да се измери прифаќањето кај 900 луѓе во 40 филијали за еден месец. Другите опции користат вистински техники, но на погрешно место: спонзорот и девелоперите не го извршуваат процесот, а brainstorming со една група во централата дава идеи, не докази.

Where this sits in PMI

PMI Guide to Business Analysis, Elicitation knowledge area (observation, surveys and questionnaires, interviews, focus groups); Business Analysis for Practitioners: A Practice Guide, 2nd ed., elicitation chapter (selecting techniques)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0051)

Progress is kept only on this device, in the browser - no sign-in, no cookies, no server. Clearing the browser’s data clears it too.

Original practice questions written and reviewed by chapter volunteers. They are not PMI exam questions, are not endorsed by PMI and are no substitute for PMI’s official materials; they count towards no education hours and no PDUs. The exam is in English; the questions here are too. “PMI”, “CAPM”, “PMP” and “PMBOK” are registered marks of Project Management Institute, Inc. The chapter runs no exams - apply at pmi.org.

The questions follow the 2023 CAPM® Examination Content Outline and the PMBOK® Guide - Seventh Edition, which PMI names for this exam. When PMI revises the outline, the questions are withdrawn until they are re-mapped.