Domain 1 · 36 % of the exam22 questions

Project Management Fundamentals and Core Concepts

Every question from one domain, in the order of the outline’s tasks. The percentage is the domain’s weight on the exam.

The questions are in English, as the exam is. Every question has a Macedonian explanation beneath it, opened on a click. This page is also a study sheet: even without JavaScript every question has its answer and explanation under “Check the answer”.

Progress

Question 1 of 22

Fundamentals · Task 1easyone answer
Question 1. A retail chain runs its stores every day, restocking shelves and serving customers. The same company has set aside a team for eight months to open its first online store, after which the team will be dissolved. What makes the online-store effort a project rather than an operation?

Pick one answer, then check.

Check the answer

Correct answer

  • CIt has a defined end and produces something the company did not have before

The decisive test is temporary plus unique. Operations are ongoing and repetitive; a project starts, ends and leaves behind something new. A candidate who chose A confused a shared feature (resource use) with a distinguishing one; a candidate who chose D picked the definition of operations.

Why, option by option - Question 1

  • A. Both projects and operations consume resources; that is what makes them compete for the same people, not what tells them apart.

  • B. Who manages the work says nothing about its nature. In a functional organisation the same managers often run both operations and projects.

  • C. A project is temporary and creates a unique product, service or result. The eight-month team and the first-ever online store are exactly those two marks.

  • D. Repetitive, procedure-driven work that sustains a stable output is the definition of operations, the opposite of what the stem describes.

Објаснување на македонски (explanation in Macedonian)

Проектот е привремен и создава единствен производ, услуга или резултат; тимот што работи осум месеци на првата онлајн-продавница ги има токму тие две обележја. Опцијата D ги опишува операциите, а тоа што се трошат ресурси (A) е заедничко и за проектите и за операциите.

Where this sits in PMI

PMBOK Guide 7th ed., The Standard for Project Management, section on creating value and the project environment; Process Groups: A Practice Guide, introduction, projects and operations

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0001)

Question 2 of 22

Fundamentals · Task 1easyone answer
Question 2. A bank places three related projects under one manager because coordinating them delivers benefits that none of them would deliver on its own. What is this grouping called?

Pick one answer, then check.

Check the answer

Correct answer

  • AA program

The words that decide it are related and benefits from coordination. A program exists to obtain those benefits; a portfolio exists to choose and balance investments against strategy, whether or not its components are related. A candidate who chose B saw a grouping and reached for the widest term without checking the reason for the grouping.

Why, option by option - Question 2

  • A. A program is a group of related projects and activities managed in a coordinated way to obtain benefits not available from managing them individually, which is exactly the reason given in the stem.

  • B. A portfolio groups projects, programs and operations to meet strategic objectives; its components need not be related to one another, and the grouping is about investment choice rather than coordinated benefits.

  • C. A subproject is a smaller, more manageable piece of a single project, not a grouping of several projects.

  • D. A phase is a collection of logically related activities within one project's life cycle, not a way of grouping separate projects.

Објаснување на македонски (explanation in Macedonian)

Програма е група поврзани проекти што се управуваат координирано за да се добијат придобивки што не би се постигнале поединечно. Портфолиото ги групира проектите и програмите според стратешките цели и тие не мора да бидат меѓусебно поврзани. Потпроектот и фазата се делови на еден проект.

Where this sits in PMI

PMBOK Guide 7th ed., The Standard for Project Management, section on the system for value delivery; Process Groups: A Practice Guide, introduction, relationship between portfolios, programs and projects

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0002)

Question 3 of 22

Fundamentals · Task 1mediumone answer
Question 3. A municipality's park-renovation plan treats the council's confirmation of the budget before the planting season as certain, although the vote has not been held. The contractor must finish before the first frost, and last week a delivery of paving stones arrived damaged. How should the plan's reliance on the budget vote be recorded?

Pick one answer, then check.

Check the answer

Correct answer

  • DAs an assumption, because the plan treats an unconfirmed event as true

The four terms are separated by time and certainty. The frost date is a constraint (a fixed limit), the damaged delivery is an issue (it has happened), the vote failing would be a risk (it may happen), and the plan's reliance on the vote passing is an assumption (treated as true without proof). A candidate who chose B was not wrong that a risk exists; the risk is the consequence of the assumption, and the stem asks about the assumption.

Why, option by option - Question 3

  • A. An issue is a condition that has already happened and needs resolution, such as the damaged paving stones. The vote has neither passed nor failed, so nothing has occurred yet.

  • B. A refusal is indeed a risk that flows from this planning basis, and it belongs in the risk register. But the stem asks how the basis itself is recorded, and a factor the plan treats as true without proof is an assumption from which the risk is then derived.

  • C. A constraint is a fixed limit imposed on the project, like finishing before the frost. An amount that has not been confirmed cannot yet act as a limit.

  • D. An assumption is a factor considered true, real or certain for planning purposes without proof. The plan is built on the vote passing in time, which is exactly that.

Објаснување на македонски (explanation in Macedonian)

Претпоставка е фактор што планот го смета за точен без доказ, како гласањето за буџетот што уште не е одржано. Ризик е тоа што советот би можел да одбие, ограничување е рокот пред мразот, а оштетените плочки се issue што веќе се случил. Претпоставката е основата, а ризикот произлегува од неа.

Where this sits in PMI

PMBOK Guide 7th ed., Models, methods and artifacts, logs and registers; Process Groups: A Practice Guide, planning process group, assumption log and risk register

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0003)

Question 4 of 22

Fundamentals · Task 1mediumone answer
Question 4. On a road-construction project the project manager has confirmed that a subcontractor altered material test results before submitting them to the client. The sponsor asks the project manager to leave this out of the next status report because a payment milestone depends on it. What should the project manager do?

Pick one answer, then check.

Check the answer

Correct answer

  • BReport the finding accurately through the project's agreed channels and tell the sponsor beforehand that this is what will happen

The Code of Ethics asks for honesty (accurate, timely information), responsibility (reporting unethical conduct) and respect (dealing directly with the person concerned). Option B satisfies all three and stays within the agreed governance. C is honest with one party and misleading with the rest; D jumps to the strongest external escalation before the project's own process has been given a chance. A candidate who chose D mistook the seriousness of the finding for a licence to skip the sequence.

Why, option by option - Question 4

  • A. The sponsor's authority does not extend to asking for a misleading report. The Code of Ethics places honesty above a superior's instruction, and a private note does not make an incomplete report accurate.

  • B. Honesty and responsibility require accurate reporting of material facts, and respect requires the sponsor to hear it directly rather than be surprised. This keeps both the information and the relationship intact and stays inside the project's governance.

  • C. This avoids one falsehood by creating a back channel. It still produces a status report the project manager knows to be incomplete and steps outside the project's agreed reporting path.

  • D. Stopping work and going to the client's lawyers are escalations the project manager has not yet earned by following the project's own process. The finding must be reported and dealt with first; legal escalation may follow if governance fails.

Објаснување на македонски (explanation in Macedonian)

Code of Ethics бара точно и навремено известување, одговорност да се пријави неетичко однесување и почит кон луѓето со кои се работи. Проектниот менаџер ја пријавува измената точно преку договорените канали и претходно му кажува на спонзорот. Опцијата C прикрива од едни, а открива на други; опцијата D ескалира надвор од проектот пред да се испочитува процесот.

Where this sits in PMI

PMI Code of Ethics and Professional Conduct, honesty, responsibility and respect sections; PMBOK Guide 7th ed., principles, being a diligent, respectful and caring steward

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0004)

Question 5 of 22

Fundamentals · Task 1mediummultiple answers
Question 5. A hospital is about to start work on a patient-scheduling application and is choosing between a predictive and an adaptive development approach. Which two characteristics of the work make an adaptive approach the better fit? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • BClinic staff can only say what they need after trying early working versions
  • EThe hospital wants small usable pieces released to wards every few weeks and adjusted from feedback

The suitability of an adaptive approach rises with uncertainty in requirements and with the value of frequent delivery and feedback. B (requirements emerge from use) and E (frequent usable releases adjusted from feedback) are both of that kind. A, C and D each describe stability or certainty, which makes a predictive approach the natural fit. A candidate who keyed A may have read a regulator as a sign of complexity; it is a sign of fixed scope.

Why, option by option - Question 5

  • A. Fixed, externally approved acceptance criteria are a stability signal; they favour defining the scope up front and building to it, a predictive trait.

  • B. Requirements that emerge from use rather than from analysis are the classic reason to choose an adaptive approach, which exists to discover scope through short cycles and feedback.

  • C. A fully specified scope under a fixed price is the strongest argument for a predictive approach, where the plan is baselined and changes are controlled formally.

  • D. Well-understood technology lowers uncertainty, which reduces the need for the experimentation that an adaptive approach provides.

  • E. Frequent incremental delivery with adjustment from feedback is the delivery cadence adaptive approaches are built around.

Објаснување на македонски (explanation in Macedonian)

Агилен, односно адаптивен пристап е најсоодветен кога барањата се откриваат преку употреба (B) и кога се сака честа испорака на мали употребливи делови со прилагодување според повратните информации (E). Фиксни критериуми за прифаќање, целосно дефиниран опсег со фиксна цена и добро позната технологија се знаци на стабилност што одат во прилог на предвидлив пристап.

Where this sits in PMI

Agile Practice Guide, life cycle selection and the suitability filter; PMBOK Guide 7th ed., Development approach and life cycle performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0005)

Question 6 of 22

Fundamentals · Task 1easyone answer
Question 6. An NGO's leadership describes its new project as the way the organisation gets from paper case files to a shared digital system. Which statement best expresses what the project is for the organisation?

Pick one answer, then check.

Check the answer

Correct answer

  • DA means of moving the organisation from its current state to a desired future state

Change is one of the principles of project management; projects are the mechanism through which organisations realise their intended change and its benefits. The stem's own language, getting from one way of working to another, points to D. A candidate who chose B mixed the project with the operations that will sustain its result.

Why, option by option - Question 6

  • A. This describes the funding boundary of the project, not its purpose. Framing a project as an expense misses the outcome it exists to bring about.

  • B. Keeping the system running after go-live is operations, which the project hands over to. The project itself is temporary.

  • C. Governance structures set decision rights and oversight; they are not what moves the organisation from one way of working to another.

  • D. Projects are how organisations bring about change, taking them from the present state (paper files) to a chosen future state (a shared digital system) and enabling the outcomes that come with it.

Објаснување на македонски (explanation in Macedonian)

Проектот е средство со кое организацијата преминува од сегашната во посакуваната идна состојба, овде од хартиени досиеја кон заеднички дигитален систем. Одржувањето на системот по пуштањето е операција, а не проект. Промената е еден од принципите на управувањето со проекти.

Where this sits in PMI

PMBOK Guide 7th ed., principles, enabling change to achieve the envisioned future state; PMBOK Guide 7th ed., The Standard for Project Management, creating value

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0006)

Question 7 of 22

Fundamentals · Task 2mediumone answer
Question 7. On a factory-line upgrade, the project manager learns that the sole supplier of a control unit has announced a two-month production halt, an event the team identified during planning. What should the project manager use the risk register to find out?

Pick one answer, then check.

Check the answer

Correct answer

  • AThe response that was planned for this event and who owns carrying it out

A risk register is used, not just kept. When an identified risk occurs, its practical value is the planned response and the named owner, which turn a surprise into an executed plan. Scores, categories and secondary risks all live in the same register but answer different questions at different times. A candidate who chose B may have treated the register as an analysis document rather than as an action document.

Why, option by option - Question 7

  • A. The register records, for each identified risk, the agreed response and the risk owner. Once the event occurs, those two entries tell the project manager what happens next and who is accountable for it.

  • B. Probability and impact are in the register, but they served to rank the risk before it happened. Now that it has occurred, the probability is no longer a question and the scores do not tell anyone what to do.

  • C. Secondary risks are recorded once a response is chosen and are worth re-checking, but only after the planned response itself has been identified and set in motion.

  • D. Categorisation helps organise and analyse risks during planning. It does not guide the response to a risk that has just materialised.

Објаснување на македонски (explanation in Macedonian)

Регистарот на ризици се користи, а не само се води. Кога ќе се случи идентификуван ризик, вредноста на регистарот е во планираниот одговор и во сопственикот на ризикот што ќе го спроведе. Веројатноста и влијанието служеле за рангирање пред настанот, а категоријата и секундарните ризици не кажуваат што да се направи сега.

Where this sits in PMI

PMBOK Guide 7th ed., Uncertainty performance domain and the risk register under artifacts; Process Groups: A Practice Guide, planning process group, plan risk responses, and monitoring and controlling, monitor risks

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0007)

Question 8 of 22

Fundamentals · Task 2mediumone answer
Question 8. Midway through a water-metering project, the project manager must decide whom to invite to a meeting on switching to a different meter model. The decision depends on knowing which people around the project have authority over the choice, which are merely affected by it, and how each has reacted to the project so far. Which document gives the project manager that information?

Pick one answer, then check.

Check the answer

Correct answer

  • CThe stakeholder register

The stem describes the three things a stakeholder register is built to answer: power or authority, interest or impact, and current attitude. The communications plan is the runner-up because it is derived from the register, but it is about the flow of information rather than the assessment of people. A candidate who chose B mistook responsibility for work with influence over a decision.

Why, option by option - Question 8

  • A. The communications plan says what each audience receives, how often and in which format. It relies on the analysis in the register rather than containing the authority, interest and attitude of each person.

  • B. A responsibility assignment matrix maps team members to work packages or deliverables. It shows who does the work, not who has influence over a decision or how outsiders feel about the project.

  • C. The register holds, for each identified person or group, their role, interest, influence and level of engagement. That is exactly the combination of authority, impact and attitude the invitation list requires.

  • D. The charter names the sponsor and lists key stakeholders at a high level at initiation. It is not maintained as the project progresses and does not track how each person has reacted.

Објаснување на македонски (explanation in Macedonian)

Stakeholder register содржи, за секоја засегната страна, улога, влијание, интерес и однос кон проектот, а тоа е токму она што му треба на проектниот менаџер за да одлучи кого да покани. Планот за комуникација кажува што и колку често добива секоја група, а матрицата за правила и одговорности кажува кој ја врши работата.

Where this sits in PMI

PMBOK Guide 7th ed., Stakeholder performance domain and the stakeholder register under artifacts; Process Groups: A Practice Guide, initiating process group, identify stakeholders

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0008)

Question 9 of 22

Fundamentals · Task 2easyone answer
Question 9. The schedule for an online-banking release lists an entry called Security sign-off received next to activities such as Build login module, 12 days, and Run penetration test, 5 days. How does the sign-off entry differ from the activities around it?

Pick one answer, then check.

Check the answer

Correct answer

  • BIt has no duration and marks a significant point in the schedule

Activities have durations because they represent work; milestones have none because they represent a point that is reached, such as an approval, a delivery or a phase gate. A candidate who chose C mixed a milestone with a summary activity, which is the neighbouring schedule element that also appears without its own work content.

Why, option by option - Question 9

  • A. Waiting for an approval may take calendar time, but that waiting is modelled as lag or as a separate activity, not as the entry itself. The sign-off is an event, not a stretch of work.

  • B. A milestone is a significant point or event in the project; it is recorded with zero duration because nothing is being worked on, only reached.

  • C. A summary activity or hammock rolls up a group of activities into one bar. A milestone stands at a point and carries no roll-up of effort.

  • D. Resources are assigned to activities that consume effort. An approval point consumes none, so it cannot carry the largest share.

Објаснување на македонски (explanation in Macedonian)

Одредницата е значајна точка во временскиот распоред и има нулто времетраење, бидејќи не се работи на неа, туку се достигнува. Активностите како градењето на модулот имаат времетраење и ресурси. Опцијата C го опишува сумарниот елемент што ги обединува активностите, а не одредницата.

Where this sits in PMI

Process Groups: A Practice Guide, planning process group, define activities and milestone list; PMBOK Guide 7th ed., Planning performance domain, scheduling

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0009)

Question 10 of 22

Fundamentals · Task 2easyone answer
Question 10. A logistics company's warehouse-automation project has completed its last work package and the client has formally accepted the result. Which activity belongs to closing the project?

Pick one answer, then check.

Check the answer

Correct answer

  • DHanding the automated system to the operations team with its documentation

Closing a project or phase means finalising all activities: confirming acceptance, transferring the product or result to operations or the customer, releasing resources, capturing lessons learned and archiving. Of the four, only the hand-over to operations is that kind of activity. A candidate who chose B may have thought a finished project needs a final baseline; it needs a final record of actuals instead.

Why, option by option - Question 10

  • A. Moving work into a next iteration belongs to an ongoing adaptive delivery cycle. Once the final deliverable is accepted, there is no next iteration inside this project.

  • B. Baselines are changed through change control while the work is under way. At closure, actuals are recorded against the final baseline for lessons learned; the baseline itself is not rewritten.

  • C. Defining new scope is initiating work, for a new phase or a new project. It is not part of bringing the current project to an orderly end.

  • D. Transitioning the deliverable to the people who will run it, together with what they need to run it, is a core part of closing, alongside final reporting, releasing the team and archiving records.

Објаснување на македонски (explanation in Macedonian)

Затворањето на проектот значи формално прифаќање, предавање на испораката на операциите заедно со документацијата, ослободување на тимот и архивирање. Пренесувањето на системот на оперативниот тим е токму таква активност. Преговарањето за нова фаза е иницирање, а не затворање.

Where this sits in PMI

Process Groups: A Practice Guide, closing process group, close project or phase; PMBOK Guide 7th ed., Delivery performance domain (closing a project or phase)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0010)

Question 11 of 22

Fundamentals · Task 2mediummultiple answers
Question 11. A project manager at a furniture maker is assembling the project management plan for the launch of a new chair range. Which three of the following are components of the project management plan rather than descriptions of the product itself? (Choose three)

Pick three answers, then check.

Check the answer

Correct answers

  • AThe scope management plan
  • CThe schedule baseline
  • EThe change management plan

The project management plan is made of subsidiary plans and baselines that describe how the project is run. Product documents, the roadmap and the bill of materials, describe the product and its future beyond the project and are owned by product management or engineering. A candidate who keyed B likely reasoned that a roadmap is a plan; it is, but for the product's life, not for this project's execution.

Why, option by option - Question 11

  • A. The scope management plan is a subsidiary plan describing how scope will be defined, validated and controlled. It is a standard component of the project management plan.

  • B. A roadmap belongs to product management. It outlines the direction of the product across its life, which extends well beyond this project's end, and it is owned by the product function.

  • C. Baselines for scope, schedule and cost are components of the project management plan; the schedule baseline is the approved version against which time performance is measured.

  • D. A bill of materials describes what the product is made of. It is a product specification, part of the deliverable, not a plan for how the project will be managed.

  • E. The change management plan describes how change requests will be submitted, evaluated and approved. It is a subsidiary plan within the project management plan.

Објаснување на македонски (explanation in Macedonian)

Проект менаџмент планот се состои од помошни планови и основни линии што кажуваат како ќе се управува проектот, како планот за опсег, основната линија на временскиот распоред и планот за управување со промени. Roadmap на производот и bill of materials го опишуваат производот и неговиот живот по проектот и припаѓаат на управувањето со производот.

Where this sits in PMI

Process Groups: A Practice Guide, planning process group, develop project management plan and its components; PMBOK Guide 7th ed., Models, methods and artifacts, plans and baselines, and Appendix X4, product management considerations

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0011)

Question 12 of 22

Fundamentals · Task 3hardone answer
Question 12. The sponsor of a hospital's records-migration project has begun attending the team's daily meetings, moving tasks between developers and asking to approve every test plan. The project is slipping and the team no longer knows who directs the work. What should the project manager do?

Pick one answer, then check.

Check the answer

Correct answer

  • AMeet the sponsor privately, describe the effect on the team, and agree how the sponsor's role differs from directing the daily work

Sponsor and project manager share accountability for the project but not the same work: the sponsor sets direction, secures resources and decides what is beyond the project manager; the project manager plans and directs the team. When the roles blur, the PMI mindset is to assess and address directly before escalating, and to understand before prescribing. A and D both restore the roles; A does it by listening first, which is why it is better. C is what follows if A fails, not what comes first.

Why, option by option - Question 12

  • A. The sponsor provides resources, removes obstacles, makes decisions above the project manager's authority and champions the project; the project manager directs the team. A direct, respectful conversation that restores that division is the first and least disruptive step.

  • B. The sponsor's authority is over funding, priorities and decisions above the project manager's level, not over daily assignments. Passing the team to the sponsor abandons the project manager's own role.

  • C. Governance is the right place if the conversation fails. Going there first escalates over the sponsor's head before the project manager has tried to resolve it directly, which damages the relationship the project depends on.

  • D. This is the right outcome delivered as a demand, without hearing why the sponsor is stepping in. It may be that the sponsor has lost confidence, which a conversation would surface and a rule would not.

Објаснување на македонски (explanation in Macedonian)

Спонзорот обезбедува ресурси, отстранува пречки и одлучува над нивото на проектниот менаџер, а проектниот менаџер го води секојдневното работење на тимот. Кога улогите се мешаат, прво се разговара директно со спонзорот, со почит и со опис на последиците. Ескалацијата до управниот комитет (C) доаѓа само ако разговорот не успее, а барањето (D) е ист резултат без слушање.

Where this sits in PMI

Process Groups: A Practice Guide, the role of the project manager and the project sponsor; PMBOK Guide 7th ed., Team performance domain, leadership and the project manager's role in the project environment

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0012)

Question 13 of 22

Fundamentals · Task 3easyone answer
Question 13. On a university campus-network project, the project manager spends Monday updating the schedule, checking spend against the budget and assigning the week's tasks. On Tuesday the project manager explains to the team why the project matters to students and invites them to shape the approach. Which term describes the Tuesday activities?

Pick one answer, then check.

Check the answer

Correct answer

  • BLeadership, because they influence people through purpose and shared ownership

Management directs people and work through established means, plans, budgets, assignments and controls; leadership guides and influences people through vision, motivation and involvement. Monday is management, Tuesday is leadership, and a project manager needs both. A candidate who chose D saw a group setting and reached for the facilitator role, which is one of the tools of leadership rather than the thing itself.

Why, option by option - Question 13

  • A. Management is about processes, plans and control, the Monday work of schedules, budgets and assignments. Tuesday is not about the plan at all.

  • B. Leadership works through vision, motivation and involving people in how the goal is reached. Explaining why the project matters and inviting the team to shape the approach is that, not a control activity.

  • C. Controlling is measuring performance against the plan and acting on variances. Nothing on Tuesday measures anything.

  • D. Facilitation is guiding a group through a process to its own outcome. Tuesday's activities may happen in a meeting, but their essence is giving purpose and ownership, which is leadership.

Објаснување на македонски (explanation in Macedonian)

Management значи насочување на работата преку планови, буџети, задачи и контрола, како во понеделникот. Leadership значи влијание врз луѓето преку цел, мотивација и вклучување, како во вторникот, кога проектниот менаџер објаснува зошто проектот е важен и го поканува тимот да го обликува пристапот. Проектниот менаџер ги користи и двете.

Where this sits in PMI

PMBOK Guide 7th ed., principles, demonstrate leadership behaviours, and Team performance domain, management and leadership; Process Groups: A Practice Guide, the role of the project manager

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0013)

Question 14 of 22

Fundamentals · Task 3mediumone answer
Question 14. During a sprint review at a software firm, a developer responds sharply when a stakeholder criticises a feature, and the room falls silent. The project manager notices their own irritation rising. Which response shows emotional intelligence?

Pick one answer, then check.

Check the answer

Correct answer

  • CPause, acknowledge that the feedback is hard to hear, and bring the discussion back to what the stakeholder needs from the feature

Emotional intelligence is the ability to recognise one's own emotions and those of others and to use that awareness to guide behaviour. The stem gives the project manager a rising emotion and a room full of them; the emotionally intelligent response regulates the first and addresses the second while keeping the meeting on its purpose. A candidate who chose A mistook decisiveness for awareness; one who chose D mistook avoidance for calm.

Why, option by option - Question 14

  • A. Public correction protects the stakeholder at the developer's expense and adds a second sharp exchange to the first. Emotional intelligence includes empathy for the person under pressure, not only the person offended.

  • B. Avoidance leaves the feeling in the room unaddressed and the stakeholder's concern unanswered. Recognising emotion means naming it, not skipping past it.

  • C. This is self-awareness (noticing the irritation and pausing), self-regulation (not acting on it), empathy (naming the difficulty) and relationship management (redirecting to the shared goal), the four parts of emotional intelligence in one move.

  • D. Routing feedback around the team removes the live conversation the review exists for. It manages the project manager's discomfort rather than the people in the room.

Објаснување на македонски (explanation in Macedonian)

Emotional intelligence е способноста да се препознаат сопствените емоции и емоциите на другите и да се управува со нив. Проектниот менаџер ја забележува сопствената нервоза, прави пауза, признава дека повратната информација тешко се слуша и го враќа разговорот кон потребата на засегнатата страна. Јавното прекорување (A) и избегнувањето (B, D) не ја решаваат ниту емоцијата ниту забелешката.

Where this sits in PMI

PMBOK Guide 7th ed., Team performance domain, emotional intelligence and interpersonal skills; Agile Practice Guide, servant leadership and team facilitation in creating an agile environment

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0014)

Question 15 of 22

Fundamentals · Task 3mediumone answer
Question 15. In a matrix organisation, a functional manager tells the project manager that the only certified welder on a pipeline project will be moved to production for four weeks to cover a seasonal peak. The welding work is on the project's critical path. In which role should the project manager respond, and how?

Pick one answer, then check.

Check the answer

Correct answer

  • DAs a negotiator, by working with the functional manager on an arrangement that serves both the production peak and the critical path

The project manager wears several hats: initiator, negotiator, listener, coach, working member and facilitator. Which one fits is decided by the situation. A resource conflict with a functional manager in a matrix is the textbook case for the negotiator, because the project manager can influence but not command. A candidate who chose C recognised the importance of listening but stopped before the part of the job that changes the outcome.

Why, option by option - Question 15

  • A. A project manager may contribute hands-on work on a small team, but certified welding is not a task to absorb, and doing so would leave the underlying resource conflict unresolved.

  • B. Cutting scope to fit a resource problem sacrifices the project's objective to avoid a conversation. Change control is for changes the project needs, not a substitute for negotiating.

  • C. Listening is part of the response, but accepting a four-week slip on the critical path without exploring alternatives is passivity, not the active listening PMI describes.

  • D. In a matrix, the project manager has no authority over the functional manager's people and must negotiate for them. Seeking a solution that meets both needs, such as a split allocation, a short deferral or a substitute, is the role the situation calls for.

Објаснување на македонски (explanation in Macedonian)

Во матрична организација проектниот менаџер нема овластување над луѓето на функционалниот менаџер и мора да преговара за ресурсите. Најдобро е да се бара решение што го задоволува и производствениот врв и критичниот пат, на пример поделено ангажирање или замена. Да се прифати доцнењето (C) е пасивно, а да се сече опсегот (B) го жртвува целта на проектот.

Where this sits in PMI

Process Groups: A Practice Guide, the role of the project manager and project resource management in a matrix organisation; PMBOK Guide 7th ed., Team performance domain, interpersonal skills including negotiation

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0015)

Question 16 of 22

Fundamentals · Task 4mediumone answer
Question 16. The risk register for an outdoor festival records the risk of storm damage as transferred to an insurer, with the venue manager as the owner of that risk. Two days before the opening, a storm damages the main stage. What should the project manager do first?

Pick one answer, then check.

Check the answer

Correct answer

  • ACheck that the venue manager has triggered the insurance claim, then assess the impact on the remaining schedule

When a planned risk response exists, following it is the first move, and the plan says two things: the insurer bears the cost and the venue manager owns the response. The project manager's job is to see that the plan runs, then to assess the schedule impact and, if needed, bring a well-formed question to the sponsor. B and D both act instead of following the plan; C escalates before assessing. A candidate who chose D may have reasoned that the stage must be rebuilt regardless, which is true, but the money and the sequence were already decided.

Why, option by option - Question 16

  • A. The response was planned, funded and assigned. Executing it means checking that the owner is carrying it out, and only then turning to the consequences for the plan. This follows the agreed strategy and assesses before acting further.

  • B. Accountability for the outcome does not mean doing the risk owner's job. Overriding the assigned owner discards the planning that put the right person in place and leaves the project manager doing two roles.

  • C. A go or no-go question may reach the sponsor later, but only once the impact is known. Escalating before assessing gives the sponsor a question without the information needed to answer it.

  • D. Spending the reserve first reverses the planned response. The transfer to the insurer was chosen so that the reserve would not have to carry this risk; drawing it down anyway leaves other identified risks unfunded.

Објаснување на македонски (explanation in Macedonian)

Кога постои планиран одговор на ризикот, прво се спроведува тој. Регистарот на ризици вели дека ризикот е пренесен на осигурителот и дека сопственик на ризикот е менаџерот на локацијата, па проектниот менаџер проверува дека тоа се случува и потоа го проценува влијанието врз временскиот распоред. Трошењето на резервата (D) го заобиколува планот, а ескалацијата до спонзорот (C) е предвремена без проценка.

Where this sits in PMI

PMBOK Guide 7th ed., Uncertainty performance domain, risk responses and implementing them; Process Groups: A Practice Guide, executing process group, implement risk responses, and monitoring and controlling, monitor risks

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0016)

Question 17 of 22

Fundamentals · Task 4easyone answer
Question 17. A city transport authority is deciding whether to approve a bus-ticketing project. One document argues why the investment is worth making; a second describes how and when the expected savings and ridership gains will be measured after the project ends. Which two documents are these?

Pick one answer, then check.

Check the answer

Correct answer

  • CThe business case and the benefits management plan

Initiation rests on two pre-project documents: the business case, which answers whether the investment is worthwhile, and the benefits management plan, which answers how the promised benefits will be realised and sustained, typically beyond the project's end. The charter follows from both. A candidate who chose D knew the business case but stopped one document short.

Why, option by option - Question 17

  • A. The charter authorises the project and the management plan says how it will be run. Neither is the justification for the investment, and neither tracks benefits after the project has closed.

  • B. A feasibility study tests whether an option can be done, and the scope statement describes what the project will deliver. The justification of value and the measurement of benefits are different documents.

  • C. The business case sets out the justification for the investment; the benefits management plan defines the benefits, how and when they will be realised and measured, and who owns them, including after closure.

  • D. The business case is the right first document, but the charter authorises the project rather than describing how benefits will be measured once it is over.

Објаснување на македонски (explanation in Macedonian)

Business case ја образложува исплатливоста на инвестицијата, а benefits management plan опишува како и кога ќе се мерат придобивките, често и по затворањето на проектот. Проектната повелба го овластува проектот и следи по нив, а физибилити-студијата само проверува дали нешто е изводливо.

Where this sits in PMI

Process Groups: A Practice Guide, project business documents (business case and benefits management plan) and initiating process group, develop project charter and its inputs; PMBOK Guide 7th ed., Models, methods and artifacts, strategy artifacts (business case)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0017)

Question 18 of 22

Fundamentals · Task 4mediumone answer
Question 18. The communications management plan for a microfinance NGO's loan-tracking project gives the regional directors a written summary every second Friday and the steering committee a dashboard each month. One regional director has started phoning the project manager every day for an update. How should the project manager respond?

Pick one answer, then check.

Check the answer

Correct answer

  • DFind out what the director actually needs and, if the plan does not provide it, revise the plan through the agreed process

A planned communication strategy is executed as written and improved through the same process that created it, not bypassed case by case. The daily calls are a signal that the plan is missing something for this stakeholder, so the project manager assesses the need, then either explains how the current arrangement meets it or revises the plan for everyone. A candidate who chose B was right to protect the plan but wrong to stop listening; one who chose A abandoned the plan altogether.

Why, option by option - Question 18

  • A. Serving one stakeholder outside the plan creates an unplanned channel, costs time the plan did not budget and leaves the other directors with less than this one receives.

  • B. Holding the line on the plan without asking why it is failing treats the plan as an end in itself. Something is not working for this stakeholder, and refusing to learn what leaves it unaddressed.

  • C. The director's problem is frequency, not detail; a monthly dashboard arrives less often than the summary already does. It also shares a governance artifact with an audience it was not designed for.

  • D. The plan is a strategy to be followed and, when it stops serving a stakeholder, to be updated deliberately. Understanding the need first and then changing the plan keeps all directors on an agreed footing.

Објаснување на македонски (explanation in Macedonian)

Планот за комуникација се следи како што е договорен, а кога престанува да ѝ служи на некоја засегната страна, се менува преку договорениот процес, а не од случај до случај. Проектниот менаџер прво дознава што навистина му треба на директорот, па ако планот не го покрива тоа, го ревидира. Дневните јавувања (A) го заобиколуваат планот, а одбивањето (B) не слуша.

Where this sits in PMI

Process Groups: A Practice Guide, executing process group, manage communications, and monitoring and controlling, monitor communications; PMBOK Guide 7th ed., Stakeholder performance domain, engagement and communication

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0018)

Question 19 of 22

Fundamentals · Task 5easyone answer
Question 19. A development team at a ticketing start-up meets for fifteen minutes each morning, standing, with every member saying what they finished yesterday, what they will work on today and what is blocking them. What is the purpose of this meeting?

Pick one answer, then check.

Check the answer

Correct answer

  • ATo coordinate the day's work among the members and surface impediments

The three questions in the stem are the shape of a daily standup, whose purpose is coordination within the team and quick detection of impediments. Reporting upward, inspecting the increment and improving the process belong to other meetings with other participants. A candidate who chose B mistook a team ritual for a reporting one.

Why, option by option - Question 19

  • A. A daily standup is the team's own synchronisation point: a shared view of where the work stands and an early warning of anything in the way, so that help can be arranged the same day.

  • B. The standup is for the people doing the work, not for reporting upward. Stakeholder reporting happens through status reports, dashboards and reviews.

  • C. Inspecting what has been built and gathering feedback on it is the purpose of a review at the end of an iteration, not a daily event.

  • D. Improving the process is the purpose of a retrospective. A standup may reveal a problem, but the discussion of how to fix the way of working is deliberately kept out of it.

Објаснување на македонски (explanation in Macedonian)

Дневниот состанок, во Scrum наречен Дневен Scrum, служи за координација на работата во тимот и за рано откривање на пречките. Известувањето кон спонзорот се прави преку извештаи, инспекцијата на инкрементот е Преглед на Спринтот, а подобрувањето на начинот на работа е ретроспектива.

Where this sits in PMI

Agile Practice Guide, common agile practices, daily standups; PMBOK Guide 7th ed., Models, methods and artifacts, meetings and events

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0019)

Question 20 of 22

Fundamentals · Task 5mediumone answer
Question 20. A project manager at a clinic needs the nursing staff to rank possible improvements to the appointment process. In earlier sessions two senior nurses did most of the talking and the others deferred to them. Which technique best fits the next session?

Pick one answer, then check.

Check the answer

Correct answer

  • BNominal group technique, so that ideas are written silently and then voted on

Two needs decide the item: quieter participants must be heard, and the output must be a ranking. Nominal group technique is the one method that builds both in, silent idea generation followed by voting. Brainstorming is the tempting neighbour because it also collects ideas from a group, but it neither protects the quiet nor ranks the result. A candidate who chose A may have known the technique without its weakness.

Why, option by option - Question 20

  • A. Brainstorming generates ideas in open discussion, which is exactly where the two senior voices have dominated before, and it does not produce a ranking on its own.

  • B. Nominal group technique has each participant write ideas independently, shares them round-robin and ranks them by vote. The silent step neutralises dominant voices and the vote delivers the ranking the project manager needs.

  • C. A focus group explores attitudes and expectations through guided conversation. It deepens the voices the project manager is trying to balance and gives no ranked outcome.

  • D. A standup is a coordination meeting for a team's own work. Giving each person a turn does not produce a prioritised list and misuses the event.

Објаснување на македонски (explanation in Macedonian)

Nominal group technique ги комбинира тивкото запишување на идеи, споделувањето по ред и гласањето, па ги неутрализира доминантните гласови и дава рангирање. Brainstorming собира идеи во отворена дискусија каде што двете постари сестри повторно би доминирале и не дава ранг. Focus group ги продлабочува ставовите, а дневниот состанок служи за координација.

Where this sits in PMI

PMI Guide to Business Analysis, elicitation techniques, brainstorming, focus groups and nominal group technique; Process Groups: A Practice Guide, planning process group, collect requirements, group creativity and decision-making techniques

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0020)

Question 21 of 22

Fundamentals · Task 5mediummultiple answers
Question 21. The weekly coordination meeting on a bridge project regularly runs over time, ends without decisions, and people leave unsure what they are expected to do. Which two changes would do most to improve the meeting's effectiveness? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • ACirculate an agenda before each meeting stating its purpose and the decisions to be made
  • DClose each meeting by recording the actions agreed, with an owner and a due date for each

An effective meeting has a purpose, the right people, a time box and a recorded outcome. The stem shows the absence of the first and the last: no clear purpose, no decisions, no assigned actions. A supplies the purpose in advance and D captures the outcome at the end. B and C make the meeting bigger and longer; E abolishes the decision-making the project needs. A candidate who keyed C may have reasoned that overrun means too little time, when it means too little structure.

Why, option by option - Question 21

  • A. An agenda with a stated purpose and named decisions gives the meeting a target, lets people prepare and makes it possible to notice when the discussion has drifted. It is the first fix for a meeting that overruns and decides nothing.

  • B. More attendees lengthen discussion and dilute ownership. Effective meetings invite the people needed for the decisions on the agenda, not everyone who might have a view.

  • C. A longer slot accommodates the drift rather than removing it. A meeting that lacks purpose and decisions will fill whatever time it is given.

  • D. Writing down actions, owners and dates converts discussion into commitments and is exactly what is missing when people leave unsure what they owe. It also gives the next meeting something concrete to follow up.

  • E. A status sheet shares information but cannot make the coordination decisions the meeting exists for. It removes the symptom by removing the decision-making, which the project still needs.

Објаснување на македонски (explanation in Macedonian)

Ефективен состанок има јасна цел, вистинските учесници, временско ограничување и запишан резултат. Агендата однапред (A) ја дава целта и одлуките што треба да се донесат, а списокот на договорени задачи со сопственик и рок (D) го претвора разговорот во обврски. Повеќе учесници или подолг термин го продлабочуваат проблемот, а табелата со статус не може да донесе одлуки.

Where this sits in PMI

PMBOK Guide 7th ed., Models, methods and artifacts, meetings and events, and Project work performance domain; Process Groups: A Practice Guide, meetings and meeting management as a tool across process groups

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0021)

Question 22 of 22

Fundamentals · Task 5easyone answer
Question 22. Before defining the requirements for a loyalty programme, a supermarket chain's project team wants to hear how a small number of regular shoppers talk about rewards in their own words and in reaction to one another. Which technique matches this purpose?

Pick one answer, then check.

Check the answer

Correct answer

  • CA focus group

The stem describes three things at once: a small group, qualitative language and interaction among participants. Those are the defining features of a focus group. Interviews are the closest neighbour, sharing the qualitative depth but not the interaction; surveys share the customer audience but not the depth. A candidate who chose D likely weighed depth and missed the phrase about reacting to one another.

Why, option by option - Question 22

  • A. A survey collects structured answers from many people at once. It scales well but captures neither people's own words nor how they respond to each other.

  • B. Brainstorming generates ideas from the project team or a working group. It is not a way of listening to customers describe their expectations.

  • C. A focus group brings a handful of prequalified participants together with a moderator to explore their expectations and attitudes through interactive conversation, which is exactly the small-group, in their own words, reacting-to-each-other purpose in the stem.

  • D. An interview is one-to-one or one-to-few and yields depth from each person, but it cannot capture the interaction between participants that the team wants to observe.

Објаснување на македонски (explanation in Macedonian)

Focus group собира мала група учесници со модератор за да ги истражи нивните ставови и очекувања преку разговор во кој реагираат еден на друг. Интервјуто дава длабочина, но еден по еден, анкетата дава бројки од многу луѓе, а brainstorming собира идеи од проектниот тим, не од купувачите.

Where this sits in PMI

PMI Guide to Business Analysis, elicitation techniques, focus groups and interviews; Business Analysis for Practitioners, elicitation, techniques for eliciting requirements

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0022)

Progress is kept only on this device, in the browser - no sign-in, no cookies, no server. Clearing the browser’s data clears it too.

Original practice questions written and reviewed by chapter volunteers. They are not PMI exam questions, are not endorsed by PMI and are no substitute for PMI’s official materials; they count towards no education hours and no PDUs. The exam is in English; the questions here are too. “PMI”, “CAPM”, “PMP” and “PMBOK” are registered marks of Project Management Institute, Inc. The chapter runs no exams - apply at pmi.org.