Test your project management skills60 questions

All questions

The whole bank, domain by domain. Good for a second pass.

The questions are in English, as the exam is. Every question has a Macedonian explanation beneath it, opened on a click. This page is also a study sheet: even without JavaScript every question has its answer and explanation under “Check the answer”.

Progress

Question 1 of 60

Fundamentals · Task 1easyone answer
Question 1. A retail chain runs its stores every day, restocking shelves and serving customers. The same company has set aside a team for eight months to open its first online store, after which the team will be dissolved. What makes the online-store effort a project rather than an operation?

Pick one answer, then check.

Check the answer

Correct answer

  • CIt has a defined end and produces something the company did not have before

The decisive test is temporary plus unique. Operations are ongoing and repetitive; a project starts, ends and leaves behind something new. A candidate who chose A confused a shared feature (resource use) with a distinguishing one; a candidate who chose D picked the definition of operations.

Why, option by option - Question 1

  • A. Both projects and operations consume resources; that is what makes them compete for the same people, not what tells them apart.

  • B. Who manages the work says nothing about its nature. In a functional organisation the same managers often run both operations and projects.

  • C. A project is temporary and creates a unique product, service or result. The eight-month team and the first-ever online store are exactly those two marks.

  • D. Repetitive, procedure-driven work that sustains a stable output is the definition of operations, the opposite of what the stem describes.

Објаснување на македонски (explanation in Macedonian)

Проектот е привремен и создава единствен производ, услуга или резултат; тимот што работи осум месеци на првата онлајн-продавница ги има токму тие две обележја. Опцијата D ги опишува операциите, а тоа што се трошат ресурси (A) е заедничко и за проектите и за операциите.

Where this sits in PMI

PMBOK Guide 7th ed., The Standard for Project Management, section on creating value and the project environment; Process Groups: A Practice Guide, introduction, projects and operations

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0001)

Question 2 of 60

Fundamentals · Task 1easyone answer
Question 2. A bank places three related projects under one manager because coordinating them delivers benefits that none of them would deliver on its own. What is this grouping called?

Pick one answer, then check.

Check the answer

Correct answer

  • AA program

The words that decide it are related and benefits from coordination. A program exists to obtain those benefits; a portfolio exists to choose and balance investments against strategy, whether or not its components are related. A candidate who chose B saw a grouping and reached for the widest term without checking the reason for the grouping.

Why, option by option - Question 2

  • A. A program is a group of related projects and activities managed in a coordinated way to obtain benefits not available from managing them individually, which is exactly the reason given in the stem.

  • B. A portfolio groups projects, programs and operations to meet strategic objectives; its components need not be related to one another, and the grouping is about investment choice rather than coordinated benefits.

  • C. A subproject is a smaller, more manageable piece of a single project, not a grouping of several projects.

  • D. A phase is a collection of logically related activities within one project's life cycle, not a way of grouping separate projects.

Објаснување на македонски (explanation in Macedonian)

Програма е група поврзани проекти што се управуваат координирано за да се добијат придобивки што не би се постигнале поединечно. Портфолиото ги групира проектите и програмите според стратешките цели и тие не мора да бидат меѓусебно поврзани. Потпроектот и фазата се делови на еден проект.

Where this sits in PMI

PMBOK Guide 7th ed., The Standard for Project Management, section on the system for value delivery; Process Groups: A Practice Guide, introduction, relationship between portfolios, programs and projects

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0002)

Question 3 of 60

Fundamentals · Task 1mediumone answer
Question 3. A municipality's park-renovation plan treats the council's confirmation of the budget before the planting season as certain, although the vote has not been held. The contractor must finish before the first frost, and last week a delivery of paving stones arrived damaged. How should the plan's reliance on the budget vote be recorded?

Pick one answer, then check.

Check the answer

Correct answer

  • DAs an assumption, because the plan treats an unconfirmed event as true

The four terms are separated by time and certainty. The frost date is a constraint (a fixed limit), the damaged delivery is an issue (it has happened), the vote failing would be a risk (it may happen), and the plan's reliance on the vote passing is an assumption (treated as true without proof). A candidate who chose B was not wrong that a risk exists; the risk is the consequence of the assumption, and the stem asks about the assumption.

Why, option by option - Question 3

  • A. An issue is a condition that has already happened and needs resolution, such as the damaged paving stones. The vote has neither passed nor failed, so nothing has occurred yet.

  • B. A refusal is indeed a risk that flows from this planning basis, and it belongs in the risk register. But the stem asks how the basis itself is recorded, and a factor the plan treats as true without proof is an assumption from which the risk is then derived.

  • C. A constraint is a fixed limit imposed on the project, like finishing before the frost. An amount that has not been confirmed cannot yet act as a limit.

  • D. An assumption is a factor considered true, real or certain for planning purposes without proof. The plan is built on the vote passing in time, which is exactly that.

Објаснување на македонски (explanation in Macedonian)

Претпоставка е фактор што планот го смета за точен без доказ, како гласањето за буџетот што уште не е одржано. Ризик е тоа што советот би можел да одбие, ограничување е рокот пред мразот, а оштетените плочки се issue што веќе се случил. Претпоставката е основата, а ризикот произлегува од неа.

Where this sits in PMI

PMBOK Guide 7th ed., Models, methods and artifacts, logs and registers; Process Groups: A Practice Guide, planning process group, assumption log and risk register

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0003)

Question 4 of 60

Fundamentals · Task 1mediumone answer
Question 4. On a road-construction project the project manager has confirmed that a subcontractor altered material test results before submitting them to the client. The sponsor asks the project manager to leave this out of the next status report because a payment milestone depends on it. What should the project manager do?

Pick one answer, then check.

Check the answer

Correct answer

  • BReport the finding accurately through the project's agreed channels and tell the sponsor beforehand that this is what will happen

The Code of Ethics asks for honesty (accurate, timely information), responsibility (reporting unethical conduct) and respect (dealing directly with the person concerned). Option B satisfies all three and stays within the agreed governance. C is honest with one party and misleading with the rest; D jumps to the strongest external escalation before the project's own process has been given a chance. A candidate who chose D mistook the seriousness of the finding for a licence to skip the sequence.

Why, option by option - Question 4

  • A. The sponsor's authority does not extend to asking for a misleading report. The Code of Ethics places honesty above a superior's instruction, and a private note does not make an incomplete report accurate.

  • B. Honesty and responsibility require accurate reporting of material facts, and respect requires the sponsor to hear it directly rather than be surprised. This keeps both the information and the relationship intact and stays inside the project's governance.

  • C. This avoids one falsehood by creating a back channel. It still produces a status report the project manager knows to be incomplete and steps outside the project's agreed reporting path.

  • D. Stopping work and going to the client's lawyers are escalations the project manager has not yet earned by following the project's own process. The finding must be reported and dealt with first; legal escalation may follow if governance fails.

Објаснување на македонски (explanation in Macedonian)

Code of Ethics бара точно и навремено известување, одговорност да се пријави неетичко однесување и почит кон луѓето со кои се работи. Проектниот менаџер ја пријавува измената точно преку договорените канали и претходно му кажува на спонзорот. Опцијата C прикрива од едни, а открива на други; опцијата D ескалира надвор од проектот пред да се испочитува процесот.

Where this sits in PMI

PMI Code of Ethics and Professional Conduct, honesty, responsibility and respect sections; PMBOK Guide 7th ed., principles, being a diligent, respectful and caring steward

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0004)

Question 5 of 60

Fundamentals · Task 1mediummultiple answers
Question 5. A hospital is about to start work on a patient-scheduling application and is choosing between a predictive and an adaptive development approach. Which two characteristics of the work make an adaptive approach the better fit? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • BClinic staff can only say what they need after trying early working versions
  • EThe hospital wants small usable pieces released to wards every few weeks and adjusted from feedback

The suitability of an adaptive approach rises with uncertainty in requirements and with the value of frequent delivery and feedback. B (requirements emerge from use) and E (frequent usable releases adjusted from feedback) are both of that kind. A, C and D each describe stability or certainty, which makes a predictive approach the natural fit. A candidate who keyed A may have read a regulator as a sign of complexity; it is a sign of fixed scope.

Why, option by option - Question 5

  • A. Fixed, externally approved acceptance criteria are a stability signal; they favour defining the scope up front and building to it, a predictive trait.

  • B. Requirements that emerge from use rather than from analysis are the classic reason to choose an adaptive approach, which exists to discover scope through short cycles and feedback.

  • C. A fully specified scope under a fixed price is the strongest argument for a predictive approach, where the plan is baselined and changes are controlled formally.

  • D. Well-understood technology lowers uncertainty, which reduces the need for the experimentation that an adaptive approach provides.

  • E. Frequent incremental delivery with adjustment from feedback is the delivery cadence adaptive approaches are built around.

Објаснување на македонски (explanation in Macedonian)

Агилен, односно адаптивен пристап е најсоодветен кога барањата се откриваат преку употреба (B) и кога се сака честа испорака на мали употребливи делови со прилагодување според повратните информации (E). Фиксни критериуми за прифаќање, целосно дефиниран опсег со фиксна цена и добро позната технологија се знаци на стабилност што одат во прилог на предвидлив пристап.

Where this sits in PMI

Agile Practice Guide, life cycle selection and the suitability filter; PMBOK Guide 7th ed., Development approach and life cycle performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0005)

Question 6 of 60

Fundamentals · Task 1easyone answer
Question 6. An NGO's leadership describes its new project as the way the organisation gets from paper case files to a shared digital system. Which statement best expresses what the project is for the organisation?

Pick one answer, then check.

Check the answer

Correct answer

  • DA means of moving the organisation from its current state to a desired future state

Change is one of the principles of project management; projects are the mechanism through which organisations realise their intended change and its benefits. The stem's own language, getting from one way of working to another, points to D. A candidate who chose B mixed the project with the operations that will sustain its result.

Why, option by option - Question 6

  • A. This describes the funding boundary of the project, not its purpose. Framing a project as an expense misses the outcome it exists to bring about.

  • B. Keeping the system running after go-live is operations, which the project hands over to. The project itself is temporary.

  • C. Governance structures set decision rights and oversight; they are not what moves the organisation from one way of working to another.

  • D. Projects are how organisations bring about change, taking them from the present state (paper files) to a chosen future state (a shared digital system) and enabling the outcomes that come with it.

Објаснување на македонски (explanation in Macedonian)

Проектот е средство со кое организацијата преминува од сегашната во посакуваната идна состојба, овде од хартиени досиеја кон заеднички дигитален систем. Одржувањето на системот по пуштањето е операција, а не проект. Промената е еден од принципите на управувањето со проекти.

Where this sits in PMI

PMBOK Guide 7th ed., principles, enabling change to achieve the envisioned future state; PMBOK Guide 7th ed., The Standard for Project Management, creating value

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0006)

Question 7 of 60

Fundamentals · Task 2mediumone answer
Question 7. On a factory-line upgrade, the project manager learns that the sole supplier of a control unit has announced a two-month production halt, an event the team identified during planning. What should the project manager use the risk register to find out?

Pick one answer, then check.

Check the answer

Correct answer

  • AThe response that was planned for this event and who owns carrying it out

A risk register is used, not just kept. When an identified risk occurs, its practical value is the planned response and the named owner, which turn a surprise into an executed plan. Scores, categories and secondary risks all live in the same register but answer different questions at different times. A candidate who chose B may have treated the register as an analysis document rather than as an action document.

Why, option by option - Question 7

  • A. The register records, for each identified risk, the agreed response and the risk owner. Once the event occurs, those two entries tell the project manager what happens next and who is accountable for it.

  • B. Probability and impact are in the register, but they served to rank the risk before it happened. Now that it has occurred, the probability is no longer a question and the scores do not tell anyone what to do.

  • C. Secondary risks are recorded once a response is chosen and are worth re-checking, but only after the planned response itself has been identified and set in motion.

  • D. Categorisation helps organise and analyse risks during planning. It does not guide the response to a risk that has just materialised.

Објаснување на македонски (explanation in Macedonian)

Регистарот на ризици се користи, а не само се води. Кога ќе се случи идентификуван ризик, вредноста на регистарот е во планираниот одговор и во сопственикот на ризикот што ќе го спроведе. Веројатноста и влијанието служеле за рангирање пред настанот, а категоријата и секундарните ризици не кажуваат што да се направи сега.

Where this sits in PMI

PMBOK Guide 7th ed., Uncertainty performance domain and the risk register under artifacts; Process Groups: A Practice Guide, planning process group, plan risk responses, and monitoring and controlling, monitor risks

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0007)

Question 8 of 60

Fundamentals · Task 2mediumone answer
Question 8. Midway through a water-metering project, the project manager must decide whom to invite to a meeting on switching to a different meter model. The decision depends on knowing which people around the project have authority over the choice, which are merely affected by it, and how each has reacted to the project so far. Which document gives the project manager that information?

Pick one answer, then check.

Check the answer

Correct answer

  • CThe stakeholder register

The stem describes the three things a stakeholder register is built to answer: power or authority, interest or impact, and current attitude. The communications plan is the runner-up because it is derived from the register, but it is about the flow of information rather than the assessment of people. A candidate who chose B mistook responsibility for work with influence over a decision.

Why, option by option - Question 8

  • A. The communications plan says what each audience receives, how often and in which format. It relies on the analysis in the register rather than containing the authority, interest and attitude of each person.

  • B. A responsibility assignment matrix maps team members to work packages or deliverables. It shows who does the work, not who has influence over a decision or how outsiders feel about the project.

  • C. The register holds, for each identified person or group, their role, interest, influence and level of engagement. That is exactly the combination of authority, impact and attitude the invitation list requires.

  • D. The charter names the sponsor and lists key stakeholders at a high level at initiation. It is not maintained as the project progresses and does not track how each person has reacted.

Објаснување на македонски (explanation in Macedonian)

Stakeholder register содржи, за секоја засегната страна, улога, влијание, интерес и однос кон проектот, а тоа е токму она што му треба на проектниот менаџер за да одлучи кого да покани. Планот за комуникација кажува што и колку често добива секоја група, а матрицата за правила и одговорности кажува кој ја врши работата.

Where this sits in PMI

PMBOK Guide 7th ed., Stakeholder performance domain and the stakeholder register under artifacts; Process Groups: A Practice Guide, initiating process group, identify stakeholders

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0008)

Question 9 of 60

Fundamentals · Task 2easyone answer
Question 9. The schedule for an online-banking release lists an entry called Security sign-off received next to activities such as Build login module, 12 days, and Run penetration test, 5 days. How does the sign-off entry differ from the activities around it?

Pick one answer, then check.

Check the answer

Correct answer

  • BIt has no duration and marks a significant point in the schedule

Activities have durations because they represent work; milestones have none because they represent a point that is reached, such as an approval, a delivery or a phase gate. A candidate who chose C mixed a milestone with a summary activity, which is the neighbouring schedule element that also appears without its own work content.

Why, option by option - Question 9

  • A. Waiting for an approval may take calendar time, but that waiting is modelled as lag or as a separate activity, not as the entry itself. The sign-off is an event, not a stretch of work.

  • B. A milestone is a significant point or event in the project; it is recorded with zero duration because nothing is being worked on, only reached.

  • C. A summary activity or hammock rolls up a group of activities into one bar. A milestone stands at a point and carries no roll-up of effort.

  • D. Resources are assigned to activities that consume effort. An approval point consumes none, so it cannot carry the largest share.

Објаснување на македонски (explanation in Macedonian)

Одредницата е значајна точка во временскиот распоред и има нулто времетраење, бидејќи не се работи на неа, туку се достигнува. Активностите како градењето на модулот имаат времетраење и ресурси. Опцијата C го опишува сумарниот елемент што ги обединува активностите, а не одредницата.

Where this sits in PMI

Process Groups: A Practice Guide, planning process group, define activities and milestone list; PMBOK Guide 7th ed., Planning performance domain, scheduling

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0009)

Question 10 of 60

Fundamentals · Task 2easyone answer
Question 10. A logistics company's warehouse-automation project has completed its last work package and the client has formally accepted the result. Which activity belongs to closing the project?

Pick one answer, then check.

Check the answer

Correct answer

  • DHanding the automated system to the operations team with its documentation

Closing a project or phase means finalising all activities: confirming acceptance, transferring the product or result to operations or the customer, releasing resources, capturing lessons learned and archiving. Of the four, only the hand-over to operations is that kind of activity. A candidate who chose B may have thought a finished project needs a final baseline; it needs a final record of actuals instead.

Why, option by option - Question 10

  • A. Moving work into a next iteration belongs to an ongoing adaptive delivery cycle. Once the final deliverable is accepted, there is no next iteration inside this project.

  • B. Baselines are changed through change control while the work is under way. At closure, actuals are recorded against the final baseline for lessons learned; the baseline itself is not rewritten.

  • C. Defining new scope is initiating work, for a new phase or a new project. It is not part of bringing the current project to an orderly end.

  • D. Transitioning the deliverable to the people who will run it, together with what they need to run it, is a core part of closing, alongside final reporting, releasing the team and archiving records.

Објаснување на македонски (explanation in Macedonian)

Затворањето на проектот значи формално прифаќање, предавање на испораката на операциите заедно со документацијата, ослободување на тимот и архивирање. Пренесувањето на системот на оперативниот тим е токму таква активност. Преговарањето за нова фаза е иницирање, а не затворање.

Where this sits in PMI

Process Groups: A Practice Guide, closing process group, close project or phase; PMBOK Guide 7th ed., Delivery performance domain (closing a project or phase)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0010)

Question 11 of 60

Fundamentals · Task 2mediummultiple answers
Question 11. A project manager at a furniture maker is assembling the project management plan for the launch of a new chair range. Which three of the following are components of the project management plan rather than descriptions of the product itself? (Choose three)

Pick three answers, then check.

Check the answer

Correct answers

  • AThe scope management plan
  • CThe schedule baseline
  • EThe change management plan

The project management plan is made of subsidiary plans and baselines that describe how the project is run. Product documents, the roadmap and the bill of materials, describe the product and its future beyond the project and are owned by product management or engineering. A candidate who keyed B likely reasoned that a roadmap is a plan; it is, but for the product's life, not for this project's execution.

Why, option by option - Question 11

  • A. The scope management plan is a subsidiary plan describing how scope will be defined, validated and controlled. It is a standard component of the project management plan.

  • B. A roadmap belongs to product management. It outlines the direction of the product across its life, which extends well beyond this project's end, and it is owned by the product function.

  • C. Baselines for scope, schedule and cost are components of the project management plan; the schedule baseline is the approved version against which time performance is measured.

  • D. A bill of materials describes what the product is made of. It is a product specification, part of the deliverable, not a plan for how the project will be managed.

  • E. The change management plan describes how change requests will be submitted, evaluated and approved. It is a subsidiary plan within the project management plan.

Објаснување на македонски (explanation in Macedonian)

Проект менаџмент планот се состои од помошни планови и основни линии што кажуваат како ќе се управува проектот, како планот за опсег, основната линија на временскиот распоред и планот за управување со промени. Roadmap на производот и bill of materials го опишуваат производот и неговиот живот по проектот и припаѓаат на управувањето со производот.

Where this sits in PMI

Process Groups: A Practice Guide, planning process group, develop project management plan and its components; PMBOK Guide 7th ed., Models, methods and artifacts, plans and baselines, and Appendix X4, product management considerations

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0011)

Question 12 of 60

Fundamentals · Task 3hardone answer
Question 12. The sponsor of a hospital's records-migration project has begun attending the team's daily meetings, moving tasks between developers and asking to approve every test plan. The project is slipping and the team no longer knows who directs the work. What should the project manager do?

Pick one answer, then check.

Check the answer

Correct answer

  • AMeet the sponsor privately, describe the effect on the team, and agree how the sponsor's role differs from directing the daily work

Sponsor and project manager share accountability for the project but not the same work: the sponsor sets direction, secures resources and decides what is beyond the project manager; the project manager plans and directs the team. When the roles blur, the PMI mindset is to assess and address directly before escalating, and to understand before prescribing. A and D both restore the roles; A does it by listening first, which is why it is better. C is what follows if A fails, not what comes first.

Why, option by option - Question 12

  • A. The sponsor provides resources, removes obstacles, makes decisions above the project manager's authority and champions the project; the project manager directs the team. A direct, respectful conversation that restores that division is the first and least disruptive step.

  • B. The sponsor's authority is over funding, priorities and decisions above the project manager's level, not over daily assignments. Passing the team to the sponsor abandons the project manager's own role.

  • C. Governance is the right place if the conversation fails. Going there first escalates over the sponsor's head before the project manager has tried to resolve it directly, which damages the relationship the project depends on.

  • D. This is the right outcome delivered as a demand, without hearing why the sponsor is stepping in. It may be that the sponsor has lost confidence, which a conversation would surface and a rule would not.

Објаснување на македонски (explanation in Macedonian)

Спонзорот обезбедува ресурси, отстранува пречки и одлучува над нивото на проектниот менаџер, а проектниот менаџер го води секојдневното работење на тимот. Кога улогите се мешаат, прво се разговара директно со спонзорот, со почит и со опис на последиците. Ескалацијата до управниот комитет (C) доаѓа само ако разговорот не успее, а барањето (D) е ист резултат без слушање.

Where this sits in PMI

Process Groups: A Practice Guide, the role of the project manager and the project sponsor; PMBOK Guide 7th ed., Team performance domain, leadership and the project manager's role in the project environment

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0012)

Question 13 of 60

Fundamentals · Task 3easyone answer
Question 13. On a university campus-network project, the project manager spends Monday updating the schedule, checking spend against the budget and assigning the week's tasks. On Tuesday the project manager explains to the team why the project matters to students and invites them to shape the approach. Which term describes the Tuesday activities?

Pick one answer, then check.

Check the answer

Correct answer

  • BLeadership, because they influence people through purpose and shared ownership

Management directs people and work through established means, plans, budgets, assignments and controls; leadership guides and influences people through vision, motivation and involvement. Monday is management, Tuesday is leadership, and a project manager needs both. A candidate who chose D saw a group setting and reached for the facilitator role, which is one of the tools of leadership rather than the thing itself.

Why, option by option - Question 13

  • A. Management is about processes, plans and control, the Monday work of schedules, budgets and assignments. Tuesday is not about the plan at all.

  • B. Leadership works through vision, motivation and involving people in how the goal is reached. Explaining why the project matters and inviting the team to shape the approach is that, not a control activity.

  • C. Controlling is measuring performance against the plan and acting on variances. Nothing on Tuesday measures anything.

  • D. Facilitation is guiding a group through a process to its own outcome. Tuesday's activities may happen in a meeting, but their essence is giving purpose and ownership, which is leadership.

Објаснување на македонски (explanation in Macedonian)

Management значи насочување на работата преку планови, буџети, задачи и контрола, како во понеделникот. Leadership значи влијание врз луѓето преку цел, мотивација и вклучување, како во вторникот, кога проектниот менаџер објаснува зошто проектот е важен и го поканува тимот да го обликува пристапот. Проектниот менаџер ги користи и двете.

Where this sits in PMI

PMBOK Guide 7th ed., principles, demonstrate leadership behaviours, and Team performance domain, management and leadership; Process Groups: A Practice Guide, the role of the project manager

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0013)

Question 14 of 60

Fundamentals · Task 3mediumone answer
Question 14. During a sprint review at a software firm, a developer responds sharply when a stakeholder criticises a feature, and the room falls silent. The project manager notices their own irritation rising. Which response shows emotional intelligence?

Pick one answer, then check.

Check the answer

Correct answer

  • CPause, acknowledge that the feedback is hard to hear, and bring the discussion back to what the stakeholder needs from the feature

Emotional intelligence is the ability to recognise one's own emotions and those of others and to use that awareness to guide behaviour. The stem gives the project manager a rising emotion and a room full of them; the emotionally intelligent response regulates the first and addresses the second while keeping the meeting on its purpose. A candidate who chose A mistook decisiveness for awareness; one who chose D mistook avoidance for calm.

Why, option by option - Question 14

  • A. Public correction protects the stakeholder at the developer's expense and adds a second sharp exchange to the first. Emotional intelligence includes empathy for the person under pressure, not only the person offended.

  • B. Avoidance leaves the feeling in the room unaddressed and the stakeholder's concern unanswered. Recognising emotion means naming it, not skipping past it.

  • C. This is self-awareness (noticing the irritation and pausing), self-regulation (not acting on it), empathy (naming the difficulty) and relationship management (redirecting to the shared goal), the four parts of emotional intelligence in one move.

  • D. Routing feedback around the team removes the live conversation the review exists for. It manages the project manager's discomfort rather than the people in the room.

Објаснување на македонски (explanation in Macedonian)

Emotional intelligence е способноста да се препознаат сопствените емоции и емоциите на другите и да се управува со нив. Проектниот менаџер ја забележува сопствената нервоза, прави пауза, признава дека повратната информација тешко се слуша и го враќа разговорот кон потребата на засегнатата страна. Јавното прекорување (A) и избегнувањето (B, D) не ја решаваат ниту емоцијата ниту забелешката.

Where this sits in PMI

PMBOK Guide 7th ed., Team performance domain, emotional intelligence and interpersonal skills; Agile Practice Guide, servant leadership and team facilitation in creating an agile environment

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0014)

Question 15 of 60

Fundamentals · Task 3mediumone answer
Question 15. In a matrix organisation, a functional manager tells the project manager that the only certified welder on a pipeline project will be moved to production for four weeks to cover a seasonal peak. The welding work is on the project's critical path. In which role should the project manager respond, and how?

Pick one answer, then check.

Check the answer

Correct answer

  • DAs a negotiator, by working with the functional manager on an arrangement that serves both the production peak and the critical path

The project manager wears several hats: initiator, negotiator, listener, coach, working member and facilitator. Which one fits is decided by the situation. A resource conflict with a functional manager in a matrix is the textbook case for the negotiator, because the project manager can influence but not command. A candidate who chose C recognised the importance of listening but stopped before the part of the job that changes the outcome.

Why, option by option - Question 15

  • A. A project manager may contribute hands-on work on a small team, but certified welding is not a task to absorb, and doing so would leave the underlying resource conflict unresolved.

  • B. Cutting scope to fit a resource problem sacrifices the project's objective to avoid a conversation. Change control is for changes the project needs, not a substitute for negotiating.

  • C. Listening is part of the response, but accepting a four-week slip on the critical path without exploring alternatives is passivity, not the active listening PMI describes.

  • D. In a matrix, the project manager has no authority over the functional manager's people and must negotiate for them. Seeking a solution that meets both needs, such as a split allocation, a short deferral or a substitute, is the role the situation calls for.

Објаснување на македонски (explanation in Macedonian)

Во матрична организација проектниот менаџер нема овластување над луѓето на функционалниот менаџер и мора да преговара за ресурсите. Најдобро е да се бара решение што го задоволува и производствениот врв и критичниот пат, на пример поделено ангажирање или замена. Да се прифати доцнењето (C) е пасивно, а да се сече опсегот (B) го жртвува целта на проектот.

Where this sits in PMI

Process Groups: A Practice Guide, the role of the project manager and project resource management in a matrix organisation; PMBOK Guide 7th ed., Team performance domain, interpersonal skills including negotiation

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0015)

Question 16 of 60

Fundamentals · Task 4mediumone answer
Question 16. The risk register for an outdoor festival records the risk of storm damage as transferred to an insurer, with the venue manager as the owner of that risk. Two days before the opening, a storm damages the main stage. What should the project manager do first?

Pick one answer, then check.

Check the answer

Correct answer

  • ACheck that the venue manager has triggered the insurance claim, then assess the impact on the remaining schedule

When a planned risk response exists, following it is the first move, and the plan says two things: the insurer bears the cost and the venue manager owns the response. The project manager's job is to see that the plan runs, then to assess the schedule impact and, if needed, bring a well-formed question to the sponsor. B and D both act instead of following the plan; C escalates before assessing. A candidate who chose D may have reasoned that the stage must be rebuilt regardless, which is true, but the money and the sequence were already decided.

Why, option by option - Question 16

  • A. The response was planned, funded and assigned. Executing it means checking that the owner is carrying it out, and only then turning to the consequences for the plan. This follows the agreed strategy and assesses before acting further.

  • B. Accountability for the outcome does not mean doing the risk owner's job. Overriding the assigned owner discards the planning that put the right person in place and leaves the project manager doing two roles.

  • C. A go or no-go question may reach the sponsor later, but only once the impact is known. Escalating before assessing gives the sponsor a question without the information needed to answer it.

  • D. Spending the reserve first reverses the planned response. The transfer to the insurer was chosen so that the reserve would not have to carry this risk; drawing it down anyway leaves other identified risks unfunded.

Објаснување на македонски (explanation in Macedonian)

Кога постои планиран одговор на ризикот, прво се спроведува тој. Регистарот на ризици вели дека ризикот е пренесен на осигурителот и дека сопственик на ризикот е менаџерот на локацијата, па проектниот менаџер проверува дека тоа се случува и потоа го проценува влијанието врз временскиот распоред. Трошењето на резервата (D) го заобиколува планот, а ескалацијата до спонзорот (C) е предвремена без проценка.

Where this sits in PMI

PMBOK Guide 7th ed., Uncertainty performance domain, risk responses and implementing them; Process Groups: A Practice Guide, executing process group, implement risk responses, and monitoring and controlling, monitor risks

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0016)

Question 17 of 60

Fundamentals · Task 4easyone answer
Question 17. A city transport authority is deciding whether to approve a bus-ticketing project. One document argues why the investment is worth making; a second describes how and when the expected savings and ridership gains will be measured after the project ends. Which two documents are these?

Pick one answer, then check.

Check the answer

Correct answer

  • CThe business case and the benefits management plan

Initiation rests on two pre-project documents: the business case, which answers whether the investment is worthwhile, and the benefits management plan, which answers how the promised benefits will be realised and sustained, typically beyond the project's end. The charter follows from both. A candidate who chose D knew the business case but stopped one document short.

Why, option by option - Question 17

  • A. The charter authorises the project and the management plan says how it will be run. Neither is the justification for the investment, and neither tracks benefits after the project has closed.

  • B. A feasibility study tests whether an option can be done, and the scope statement describes what the project will deliver. The justification of value and the measurement of benefits are different documents.

  • C. The business case sets out the justification for the investment; the benefits management plan defines the benefits, how and when they will be realised and measured, and who owns them, including after closure.

  • D. The business case is the right first document, but the charter authorises the project rather than describing how benefits will be measured once it is over.

Објаснување на македонски (explanation in Macedonian)

Business case ја образложува исплатливоста на инвестицијата, а benefits management plan опишува како и кога ќе се мерат придобивките, често и по затворањето на проектот. Проектната повелба го овластува проектот и следи по нив, а физибилити-студијата само проверува дали нешто е изводливо.

Where this sits in PMI

Process Groups: A Practice Guide, project business documents (business case and benefits management plan) and initiating process group, develop project charter and its inputs; PMBOK Guide 7th ed., Models, methods and artifacts, strategy artifacts (business case)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0017)

Question 18 of 60

Fundamentals · Task 4mediumone answer
Question 18. The communications management plan for a microfinance NGO's loan-tracking project gives the regional directors a written summary every second Friday and the steering committee a dashboard each month. One regional director has started phoning the project manager every day for an update. How should the project manager respond?

Pick one answer, then check.

Check the answer

Correct answer

  • DFind out what the director actually needs and, if the plan does not provide it, revise the plan through the agreed process

A planned communication strategy is executed as written and improved through the same process that created it, not bypassed case by case. The daily calls are a signal that the plan is missing something for this stakeholder, so the project manager assesses the need, then either explains how the current arrangement meets it or revises the plan for everyone. A candidate who chose B was right to protect the plan but wrong to stop listening; one who chose A abandoned the plan altogether.

Why, option by option - Question 18

  • A. Serving one stakeholder outside the plan creates an unplanned channel, costs time the plan did not budget and leaves the other directors with less than this one receives.

  • B. Holding the line on the plan without asking why it is failing treats the plan as an end in itself. Something is not working for this stakeholder, and refusing to learn what leaves it unaddressed.

  • C. The director's problem is frequency, not detail; a monthly dashboard arrives less often than the summary already does. It also shares a governance artifact with an audience it was not designed for.

  • D. The plan is a strategy to be followed and, when it stops serving a stakeholder, to be updated deliberately. Understanding the need first and then changing the plan keeps all directors on an agreed footing.

Објаснување на македонски (explanation in Macedonian)

Планот за комуникација се следи како што е договорен, а кога престанува да ѝ служи на некоја засегната страна, се менува преку договорениот процес, а не од случај до случај. Проектниот менаџер прво дознава што навистина му треба на директорот, па ако планот не го покрива тоа, го ревидира. Дневните јавувања (A) го заобиколуваат планот, а одбивањето (B) не слуша.

Where this sits in PMI

Process Groups: A Practice Guide, executing process group, manage communications, and monitoring and controlling, monitor communications; PMBOK Guide 7th ed., Stakeholder performance domain, engagement and communication

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0018)

Question 19 of 60

Fundamentals · Task 5easyone answer
Question 19. A development team at a ticketing start-up meets for fifteen minutes each morning, standing, with every member saying what they finished yesterday, what they will work on today and what is blocking them. What is the purpose of this meeting?

Pick one answer, then check.

Check the answer

Correct answer

  • ATo coordinate the day's work among the members and surface impediments

The three questions in the stem are the shape of a daily standup, whose purpose is coordination within the team and quick detection of impediments. Reporting upward, inspecting the increment and improving the process belong to other meetings with other participants. A candidate who chose B mistook a team ritual for a reporting one.

Why, option by option - Question 19

  • A. A daily standup is the team's own synchronisation point: a shared view of where the work stands and an early warning of anything in the way, so that help can be arranged the same day.

  • B. The standup is for the people doing the work, not for reporting upward. Stakeholder reporting happens through status reports, dashboards and reviews.

  • C. Inspecting what has been built and gathering feedback on it is the purpose of a review at the end of an iteration, not a daily event.

  • D. Improving the process is the purpose of a retrospective. A standup may reveal a problem, but the discussion of how to fix the way of working is deliberately kept out of it.

Објаснување на македонски (explanation in Macedonian)

Дневниот состанок, во Scrum наречен Дневен Scrum, служи за координација на работата во тимот и за рано откривање на пречките. Известувањето кон спонзорот се прави преку извештаи, инспекцијата на инкрементот е Преглед на Спринтот, а подобрувањето на начинот на работа е ретроспектива.

Where this sits in PMI

Agile Practice Guide, common agile practices, daily standups; PMBOK Guide 7th ed., Models, methods and artifacts, meetings and events

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0019)

Question 20 of 60

Fundamentals · Task 5mediumone answer
Question 20. A project manager at a clinic needs the nursing staff to rank possible improvements to the appointment process. In earlier sessions two senior nurses did most of the talking and the others deferred to them. Which technique best fits the next session?

Pick one answer, then check.

Check the answer

Correct answer

  • BNominal group technique, so that ideas are written silently and then voted on

Two needs decide the item: quieter participants must be heard, and the output must be a ranking. Nominal group technique is the one method that builds both in, silent idea generation followed by voting. Brainstorming is the tempting neighbour because it also collects ideas from a group, but it neither protects the quiet nor ranks the result. A candidate who chose A may have known the technique without its weakness.

Why, option by option - Question 20

  • A. Brainstorming generates ideas in open discussion, which is exactly where the two senior voices have dominated before, and it does not produce a ranking on its own.

  • B. Nominal group technique has each participant write ideas independently, shares them round-robin and ranks them by vote. The silent step neutralises dominant voices and the vote delivers the ranking the project manager needs.

  • C. A focus group explores attitudes and expectations through guided conversation. It deepens the voices the project manager is trying to balance and gives no ranked outcome.

  • D. A standup is a coordination meeting for a team's own work. Giving each person a turn does not produce a prioritised list and misuses the event.

Објаснување на македонски (explanation in Macedonian)

Nominal group technique ги комбинира тивкото запишување на идеи, споделувањето по ред и гласањето, па ги неутрализира доминантните гласови и дава рангирање. Brainstorming собира идеи во отворена дискусија каде што двете постари сестри повторно би доминирале и не дава ранг. Focus group ги продлабочува ставовите, а дневниот состанок служи за координација.

Where this sits in PMI

PMI Guide to Business Analysis, elicitation techniques, brainstorming, focus groups and nominal group technique; Process Groups: A Practice Guide, planning process group, collect requirements, group creativity and decision-making techniques

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0020)

Question 21 of 60

Fundamentals · Task 5mediummultiple answers
Question 21. The weekly coordination meeting on a bridge project regularly runs over time, ends without decisions, and people leave unsure what they are expected to do. Which two changes would do most to improve the meeting's effectiveness? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • ACirculate an agenda before each meeting stating its purpose and the decisions to be made
  • DClose each meeting by recording the actions agreed, with an owner and a due date for each

An effective meeting has a purpose, the right people, a time box and a recorded outcome. The stem shows the absence of the first and the last: no clear purpose, no decisions, no assigned actions. A supplies the purpose in advance and D captures the outcome at the end. B and C make the meeting bigger and longer; E abolishes the decision-making the project needs. A candidate who keyed C may have reasoned that overrun means too little time, when it means too little structure.

Why, option by option - Question 21

  • A. An agenda with a stated purpose and named decisions gives the meeting a target, lets people prepare and makes it possible to notice when the discussion has drifted. It is the first fix for a meeting that overruns and decides nothing.

  • B. More attendees lengthen discussion and dilute ownership. Effective meetings invite the people needed for the decisions on the agenda, not everyone who might have a view.

  • C. A longer slot accommodates the drift rather than removing it. A meeting that lacks purpose and decisions will fill whatever time it is given.

  • D. Writing down actions, owners and dates converts discussion into commitments and is exactly what is missing when people leave unsure what they owe. It also gives the next meeting something concrete to follow up.

  • E. A status sheet shares information but cannot make the coordination decisions the meeting exists for. It removes the symptom by removing the decision-making, which the project still needs.

Објаснување на македонски (explanation in Macedonian)

Ефективен состанок има јасна цел, вистинските учесници, временско ограничување и запишан резултат. Агендата однапред (A) ја дава целта и одлуките што треба да се донесат, а списокот на договорени задачи со сопственик и рок (D) го претвора разговорот во обврски. Повеќе учесници или подолг термин го продлабочуваат проблемот, а табелата со статус не може да донесе одлуки.

Where this sits in PMI

PMBOK Guide 7th ed., Models, methods and artifacts, meetings and events, and Project work performance domain; Process Groups: A Practice Guide, meetings and meeting management as a tool across process groups

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0021)

Question 22 of 60

Fundamentals · Task 5easyone answer
Question 22. Before defining the requirements for a loyalty programme, a supermarket chain's project team wants to hear how a small number of regular shoppers talk about rewards in their own words and in reaction to one another. Which technique matches this purpose?

Pick one answer, then check.

Check the answer

Correct answer

  • CA focus group

The stem describes three things at once: a small group, qualitative language and interaction among participants. Those are the defining features of a focus group. Interviews are the closest neighbour, sharing the qualitative depth but not the interaction; surveys share the customer audience but not the depth. A candidate who chose D likely weighed depth and missed the phrase about reacting to one another.

Why, option by option - Question 22

  • A. A survey collects structured answers from many people at once. It scales well but captures neither people's own words nor how they respond to each other.

  • B. Brainstorming generates ideas from the project team or a working group. It is not a way of listening to customers describe their expectations.

  • C. A focus group brings a handful of prequalified participants together with a moderator to explore their expectations and attitudes through interactive conversation, which is exactly the small-group, in their own words, reacting-to-each-other purpose in the stem.

  • D. An interview is one-to-one or one-to-few and yields depth from each person, but it cannot capture the interaction between participants that the team wants to observe.

Објаснување на македонски (explanation in Macedonian)

Focus group собира мала група учесници со модератор за да ги истражи нивните ставови и очекувања преку разговор во кој реагираат еден на друг. Интервјуто дава длабочина, но еден по еден, анкетата дава бројки од многу луѓе, а brainstorming собира идеи од проектниот тим, не од купувачите.

Where this sits in PMI

PMI Guide to Business Analysis, elicitation techniques, focus groups and interviews; Business Analysis for Practitioners, elicitation, techniques for eliciting requirements

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0022)

Question 23 of 60

Predictive · Task 1easyone answer
Question 23. A regional water utility must replace the chlorination unit at one of its treatment plants. The specification is fixed by the environmental regulator, the work is let under a fixed-price contract, and the unit is of no use until it is fully installed and certified. Which development approach fits this project best?

Pick one answer, then check.

Check the answer

Correct answer

  • BPredictive

The choice of development approach follows the product and the project context. When requirements are stable and known up front, the contract fixes price and scope, and the deliverable cannot be split into independently useful parts, a predictive, plan-based approach is the fit. A candidate who chose hybrid was looking for a middle way that the situation does not call for; a candidate who chose incremental missed that the unit has no value until it is complete.

Why, option by option - Question 23

  • A. An adaptive approach suits requirements that are uncertain and expected to change through feedback. Here the requirements are fixed by a regulator before work starts, so there is nothing to discover iteratively.

  • B. Stable, externally fixed requirements, a fixed-price contract and a single deliverable that only has value when complete are the classic conditions for planning the whole scope, schedule and cost up front and then executing against baselines.

  • C. An incremental approach delivers usable pieces of the product early. A chlorination unit that cannot be used until it is installed and certified offers no increment with stand-alone value.

  • D. A hybrid approach mixes predictive and adaptive elements when part of the scope is stable and part is uncertain. Nothing in this project is uncertain enough to justify the adaptive part.

Објаснување на македонски (explanation in Macedonian)

Барањата се утврдени однапред од регулаторот, договорот е со фиксна цена, а испораката нема вредност додека не е целосно завршена. Тоа се условите во кои најдобро одговара predictive пристап, каде опсегот, временскиот распоред и трошокот се планираат целосно на почетокот. Агилен или hybrid пристап има смисла само кога дел од барањата се неизвесни.

Where this sits in PMI

PMBOK Guide 7th ed., Development Approach and Life Cycle performance domain; Process Groups: A Practice Guide, section on tailoring and development approaches

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0023)

Question 24 of 60

Predictive · Task 1mediummultiple answers
Question 24. The project manager of a bank's core-system upgrade is listing the activities that belong to the Monitoring and Controlling Process Group. Which two activities belong in that group? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • AComparing actual progress with the schedule baseline and recommending corrective action
  • DReviewing change requests and deciding whether each is approved or rejected

Monitoring and Controlling is the group of activities that track, review and regulate progress and performance, identify where the plan needs to change, and manage those changes. Comparing progress with the baseline and running integrated change control are both squarely inside it. Acquiring resources is Executing, developing the charter is Initiating, and archiving and releasing the team are Closing. A candidate who picked option B confused doing the planned work with checking it.

Why, option by option - Question 24

  • A. Measuring performance against a baseline and recommending corrective or preventive action is the core of Monitoring and Controlling; it is what Control Schedule does.

  • B. Obtaining people, equipment and services for the project is an Executing activity (Acquire Resources). It carries out the plan rather than checking performance against it.

  • C. The charter is developed in the Initiating Process Group; it authorises the project and names the project manager before any control can take place.

  • D. Perform Integrated Change Control sits in Monitoring and Controlling: every change request is reviewed, decided and recorded there so the baselines stay under control.

  • E. Archiving records and releasing resources are Closing activities, performed once the deliverables have been accepted and the project or phase ends.

Објаснување на македонски (explanation in Macedonian)

Во Process Group за мониторинг и контрола спаѓаат споредбата на напредокот со основната линија на временскиот распоред и одлучувањето за барањата за промени преку контрола на промени. Обезбедувањето ресурси е извршување, изработката на проектната повелба е иницирање, а архивирањето и ослободувањето на тимот се затворање.

Where this sits in PMI

Process Groups: A Practice Guide, Monitoring and Controlling Process Group and the Executing, Initiating and Closing Process Groups; PMBOK Guide 7th ed., Measurement performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0024)

Question 25 of 60

Predictive · Task 1mediumone answer
Question 25. A pharmaceutical manufacturer is expanding a plant in four sequential phases. At the end of the design phase, the steering committee examines the phase's deliverables against the business case and decides whether to authorise the construction phase, repeat the design work or stop the project. What is this review?

Pick one answer, then check.

Check the answer

Correct answer

  • CA phase gate

In a predictive life cycle the phases are separated by phase gates, also called stage gates or kill points: a formal review of the phase's results against the business documents and plans that ends with a go, no-go or rework decision. A milestone marks a point in time but carries no such decision; a kick-off follows the decision; a change control board rules on change requests, not on phases. A candidate who picked the milestone confused the point in the schedule with the review that happens there.

Why, option by option - Question 25

  • A. A milestone is a significant point or event in the schedule with no duration; the end of a phase is often marked by one, but a milestone is not itself a review with a continue-or-stop decision.

  • B. A kick-off meeting launches a project or phase after it has been authorised, to align the team on objectives and roles. The decision to proceed has already been made by then.

  • C. A phase gate is the review held at the end of a phase where performance and progress are compared with the business case and plans, and a decision is made to continue, continue with changes, or end the project. That is exactly what the steering committee is doing.

  • D. The change control board reviews individual change requests against the baselines. It does not decide whether the next phase of the project goes ahead.

Објаснување на македонски (explanation in Macedonian)

Прегледот на крајот од една фаза, каде управниот комитет одлучува дали проектот продолжува во следната фаза, се повторува работата или се запира, е phase gate. Одредницата е само точка во временскиот распоред без одлука, kick-off состанокот се одржува откако одлуката е донесена, а одборот за контрола на промени одлучува само за барања за промени.

Where this sits in PMI

PMBOK Guide 7th ed., Development Approach and Life Cycle performance domain (phases and phase gates); Process Groups: A Practice Guide, project life cycle and phases

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0025)

Question 26 of 60

Predictive · Task 2mediumone answer
Question 26. A warehouse fit-out project has five activities. Activity A (3 days) starts the project. Activities B (4 days) and C (5 days) both start when A finishes. Activity D (2 days) starts when both B and C have finished, and activity E (2 days) starts when B finishes. D and E are the final activities. What is the duration of the critical path?

Pick one answer, then check.

Check the answer

Correct answer

  • B10 days

The critical path method finds the longest sequence of dependent activities through the network; its length is the shortest possible project duration, and every activity on it has zero float. Listing the paths gives A-C-D at 10 days and A-B-D and A-B-E at 9 days each, so the critical path is A-C-D and the answer is 10 days. Candidates who summed everything, or who added B and C together, forgot that parallel activities overlap.

Why, option by option - Question 26

  • A. Nine days is the length of the paths A-B-D and A-B-E. They are the shorter paths through the network, so activities B and E carry one day of float; the critical path is the longest one.

  • B. The path A-C-D is 3 + 5 + 2 = 10 days. The other paths, A-B-D and A-B-E, are 3 + 4 + 2 = 9 days each. The longest path through the network is the critical path, so the project cannot finish in fewer than 10 days.

  • C. Twelve days is A + B + C, which adds the parallel activities B and C as if one had to wait for the other. They start together after A, so only the longer of the two counts.

  • D. Sixteen days is the sum of all five activities. Adding every duration ignores that B runs in parallel with C and that D runs in parallel with E.

Објаснување на македонски (explanation in Macedonian)

Според методот на критичен пат, критичниот пат е најдолгата низа зависни активности низ мрежниот дијаграм. Патот A-C-D трае 3 + 5 + 2 = 10 дена, а патиштата A-B-D и A-B-E по 9 дена, па активностите B и E имаат по еден ден float. Собирањето на сите активности или на B и C заедно ги игнорира паралелните активности.

Where this sits in PMI

Process Groups: A Practice Guide, Develop Schedule (critical path method and schedule network analysis); PMBOK Guide 7th ed., Planning performance domain (schedule)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0026)

Question 27 of 60

Predictive · Task 2easyone answer
Question 27. At the end of the fourth month of a road-resurfacing project, the earned value (EV) is EUR 320,000 and the planned value (PV) is EUR 350,000. What is the schedule variance (SV), and what does it tell the project manager?

Pick one answer, then check.

Check the answer

Correct answer

  • ASV is minus EUR 30,000, so the project is behind schedule

Schedule variance is earned value minus planned value. Here it is 320,000 - 350,000 = -30,000. A negative SV means the project has earned less value than the schedule baseline called for by this date, so it is behind schedule. SV says nothing about money spent; a candidate who read it as a budget signal mixed it up with cost variance, which compares earned value with actual cost.

Why, option by option - Question 27

  • A. SV = EV - PV = 320,000 - 350,000 = -30,000. Less value has been earned than was planned by this date, and a negative schedule variance means the work is behind the schedule baseline.

  • B. The arithmetic is right but the reading is wrong. Schedule variance compares earned value with planned value and says nothing about spending; over or under budget is read from the cost variance, which needs the actual cost.

  • C. This subtracts in the wrong order (PV - EV). With less earned than planned, the variance must be negative and the project cannot be ahead.

  • D. Both the sign and the interpretation are wrong: the order of subtraction is reversed and schedule variance does not measure cost.

Објаснување на македонски (explanation in Macedonian)

Schedule variance (SV) е earned value минус planned value, значи 320.000 − 350.000 = −30.000 евра. Негативната вредност значи дека проектот заостанува зад основната линија на временскиот распоред. SV не кажува ништо за трошокот; за тоа служи cost variance, кој бара и actual cost.

Where this sits in PMI

Process Groups: A Practice Guide, Control Schedule and Control Costs (earned value analysis); PMBOK Guide 7th ed., Measurement performance domain (earned value)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0027)

Question 28 of 60

Predictive · Task 2easyone answer
Question 28. While reviewing the work breakdown structure of a store-refit project for a retail chain, the sponsor notices that the work packages under the "Fixtures" element add up to less than all the fixture work the contract requires. Which WBS principle has been broken?

Pick one answer, then check.

Check the answer

Correct answer

  • CThe 100 percent rule

A WBS is a hierarchical decomposition of the total scope of work, and its defining principle is the 100 percent rule: each level of decomposition must contain all, and only, the work of the level above it. When the work packages under an element sum to less than the element, scope is missing from the WBS and will be missing from the schedule and budget derived from it. Rolling wave and progressive elaboration explain how detail grows; the 8/80 rule concerns work-package size.

Why, option by option - Question 28

  • A. Rolling wave planning details near-term work and leaves later work at a higher level. It is allowed in a WBS, but even a high-level element must still represent all of the work below it.

  • B. Progressive elaboration is the refining of the plan as more becomes known. It describes how detail grows over time, not whether the children of an element cover everything the parent contains.

  • C. The 100 percent rule says the WBS includes all of the project's work and that the children of any element together represent 100 percent of that element, no more and no less. Work packages that add up to less than their parent break it.

  • D. The 8/80 rule is a sizing heuristic that keeps a work package between roughly 8 and 80 hours of effort. It is about the size of a package, not about whether the packages together cover the parent.

Објаснување на македонски (explanation in Macedonian)

Структурата за поделба на работата мора да го содржи целиот опсег: работните пакети под еден елемент заедно претставуваат 100 % од тој елемент, ни повеќе ни помалку. Тоа е правилото „100 %“ (100 percent rule). Rolling wave planning и progressive elaboration опишуваат како расте деталноста, а правилото 8/80 се однесува на големината на работниот пакет.

Where this sits in PMI

Process Groups: A Practice Guide, Create WBS (decomposition and the 100 percent rule); PMBOK Guide 7th ed., Planning performance domain (scope and work breakdown structure)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0028)

Question 29 of 60

Predictive · Task 2mediumone answer
Question 29. On a predictive software project for an insurance firm, a billing module has failed its inspection. The quality management plan says defects found in inspection are repaired and re-inspected before acceptance; the repair will push the module's milestone beyond the date in the schedule baseline, and the slip cannot be recovered. The change management plan says that any change to a baseline must be formally approved before it takes effect. What should the project manager do?

Pick one answer, then check.

Check the answer

Correct answer

  • DRepair the module and re-inspect it, and submit a change request for the schedule baseline to the change control board

The project management plan is followed as agreed. The quality management plan settles what happens to a failed deliverable, so it is repaired and re-inspected. The knock-on effect on the schedule baseline is a change, and changes to baselines go through integrated change control as the change management plan requires. Option A does the first half and then bypasses change control; option B trades the plan for a date by accepting defective work, and option C treats a baseline change as an issue to be logged instead of a change to be approved.

Why, option by option - Question 29

  • A. Following the quality plan is right, but a baseline is only changed through the change control process. The project manager cannot re-baseline the schedule on their own authority, even to record a delay that is certain.

  • B. This protects the date by abandoning the quality management plan. The plan states that inspection defects are repaired before acceptance, and acceptance of known-defective work is not a decision the project manager can make alone.

  • C. Following the quality plan is right, and logging the slip is harmless, but the issue log does not authorise a change to a baseline. Only an approved change request moves the schedule baseline.

  • D. Both plans are followed as written: the quality plan decides what happens to the defective deliverable, and the change management plan decides how the resulting baseline change is handled. The board, not the project manager, approves the new baseline.

Објаснување на македонски (explanation in Macedonian)

Проект менаџмент планот се следи како што е договорен. Планот за квалитет вели дека испораката што паднала на испитување се поправа и повторно се испитува, а промената на основната линија на временскиот распоред што следува од тоа оди преку контрола на промени до одборот. Проектниот менаџер не смее сам да ја промени основната линија, ниту да прифати дефектна испорака за да ја одржи одредницата.

Where this sits in PMI

Process Groups: A Practice Guide, Control Quality and Perform Integrated Change Control; PMBOK Guide 7th ed., Delivery performance domain (quality) and Planning performance domain (baselines and change)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0029)

Question 30 of 60

Predictive · Task 3mediumone answer
Question 30. At a status meeting on a rural-clinic construction project run by a non-governmental organisation, a team member reports that the local supplier has stopped deliveries and the site has been idle for two days. The project manager wants to record this with an owner and a target date for resolution. Where should it be recorded?

Pick one answer, then check.

Check the answer

Correct answer

  • DThe issue log

The dividing line is time: a risk is uncertain and lies in the future; an issue is certain and is happening now. A supplier that has already stopped delivering is an issue, and the issue log is the artifact that assigns it an owner and a resolution date and tracks it to closure. The change log holds change requests, the risk register holds uncertain events, and the lessons learned register holds what was learned after the fact. A candidate who chose the risk register missed that the event has already occurred.

Why, option by option - Question 30

  • A. A risk is an uncertain event that may happen. The supply stoppage has already happened, so it is no longer a risk; if it had been listed as one, its entry would now be closed and the event tracked elsewhere.

  • B. The change log tracks change requests and their status. No change to scope, schedule or cost has been requested yet; that may follow, but first the problem itself must be tracked.

  • C. The lessons learned register captures what was learned and what to do differently. Once the stoppage is resolved a lesson may be recorded, but it is not the place to manage an open problem.

  • D. An issue is a current condition or event that has already happened and needs to be resolved. The issue log records it with an owner, a priority and a target date, which is exactly what the project manager wants.

Објаснување на македонски (explanation in Macedonian)

Ризикот е неизвесен настан што може да се случи; проблем што веќе се случил, како прекинатата испорака, е issue и се запишува во issue log со одговорно лице и рок за решавање. Регистарот на ризици е за неизвесни настани, change log за барања за промени, а lessons learned регистарот за наученото откако проблемот ќе се реши.

Where this sits in PMI

PMBOK Guide 7th ed., Models, Methods and Artifacts (logs and registers); Process Groups: A Practice Guide, Direct and Manage Project Work and Monitor and Control Project Work (issue log)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0030)

Question 31 of 60

Predictive · Task 3easyone answer
Question 31. Halfway through the refurbishment of a hospital ward, the project's earned value (EV) is EUR 400,000 and its actual cost (AC) is EUR 500,000. What are the cost variance (CV) and the cost performance index (CPI)?

Pick one answer, then check.

Check the answer

Correct answer

  • ACV is minus EUR 100,000 and CPI is 0.80

Cost variance is earned value minus actual cost, and the cost performance index is earned value divided by actual cost. With EV of 400,000 and AC of 500,000, CV is -100,000 and CPI is 0.80: the project is over budget and is getting 80 cents of value for every euro spent. The two measures always agree in direction, so any option that pairs a negative variance with an index above one, or a positive variance with an index below one, can be ruled out before the arithmetic.

Why, option by option - Question 31

  • A. CV = EV - AC = 400,000 - 500,000 = -100,000, and CPI = EV / AC = 400,000 / 500,000 = 0.80. Both say the same thing: the project has spent more than the value of the work it has completed.

  • B. This reverses both formulas (AC - EV and AC / EV). A project that has spent 500,000 to earn 400,000 cannot have a favourable variance or an index above one.

  • C. The variance is right but the index is AC divided by EV. CV and CPI always point the same way: a negative CV goes with a CPI below one.

  • D. The index is right but the variance is AC minus EV. A CPI below one cannot go with a positive cost variance.

Објаснување на македонски (explanation in Macedonian)

Cost variance (CV) е earned value минус actual cost, 400.000 − 500.000 = −100.000 евра, а cost performance index (CPI) е earned value поделен со actual cost, 400.000 / 500.000 = 0,80. Проектот троши повеќе од вредноста на завршената работа. Негативен CV секогаш оди со CPI помал од 1.

Where this sits in PMI

Process Groups: A Practice Guide, Control Costs (earned value analysis and variance analysis); PMBOK Guide 7th ed., Measurement performance domain (earned value)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0031)

Question 32 of 60

Predictive · Task 3easymultiple answers
Question 32. The project manager of a predictive, plan-based bridge-repair project for a municipality is assembling the artifacts used to control the project against its approved baselines. Which two artifacts belong in that set? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • BThe change log
  • EThe work performance report

Controls on a predictive project compare what is happening with what was baselined and manage any deviation through change control. The work performance report carries the comparison, with variances such as SV and CV, and the change log carries the decisions that alter the baselines. The product backlog is an artifact of adaptive delivery, the business case justifies the project rather than controlling it, and the charter authorises the project before any control exists. A candidate who picked the charter mistook an initiating artifact for a controlling one.

Why, option by option - Question 32

  • A. A product backlog is the ordered list of work in an adaptive project; it is reprioritised continually and is not measured against a baseline.

  • B. The change log records every change request and its status. Because baselines are only altered through approved changes, the log is the record of how and why the baselines have moved.

  • C. The business case justifies the project and is revisited at phase gates to confirm it still holds. It is a business document, not a control artifact; performance is measured against the baselines, not against the business case.

  • D. The charter authorises the project and gives the project manager authority. It is an initiating artifact and is not used to measure performance or to control the work against the baselines.

  • E. Work performance reports present measured performance against the baselines, such as schedule and cost variances, so that decisions and corrective actions can be taken. They are the core control document of a predictive project.

Објаснување на македонски (explanation in Macedonian)

Контролата во predictive проект значи споредба со основните линии и управување со отстапувањата преку контрола на промени. Извештајот за напредокот со schedule и cost variance ја носи споредбата, а change log ги бележи одобрените промени на основните линии. Листата на планирани активности за Продуктот е агилен артефакт, business case го оправдува проектот наместо да го контролира, а проектната повелба само го овластува проектот.

Where this sits in PMI

PMBOK Guide 7th ed., Models, Methods and Artifacts (logs, registers and reports); Process Groups: A Practice Guide, Monitor and Control Project Work and Perform Integrated Change Control

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0032)

Question 33 of 60

Agile · Task 1easyone answer
Question 33. The project management office of a public hospital wants to pilot an adaptive approach on one of four upcoming projects. Which project is the best candidate?

Pick one answer, then check.

Check the answer

Correct answer

  • CBuilding a patient-appointment app whose features the clinics expect to revise after each release goes to patients

The Agile Practice Guide distinguishes definable work (proven procedures, clear requirements, little change) from high-uncertainty work (requirements evolve, learning comes from feedback). Adaptive approaches earn their cost only where the second applies, and the appointment app is the only project whose scope is expected to change as users react. A candidate who chose the boilers or the relocation matched "important" with "adaptive"; importance is not the criterion, uncertainty and the rate of change are.

Why, option by option - Question 33

  • A. Fixed, well-understood requirements and a fixed-price contract suit a predictive life cycle, where the work is planned once and executed to the specification. Iterating would add cost without producing any learning.

  • B. The deliverable and its format are known in advance and delivered once. This is definable work with low uncertainty, the classic case for a predictive approach.

  • C. Requirements are uncertain, change is expected and feedback arrives after each release. That is the high-uncertainty, high-change situation in which an adaptive approach delivers value in small increments and adjusts the backlog as the clinics learn.

  • D. A short, repeatable task done to a proven procedure has no requirement uncertainty to resolve. Iterations and feedback loops would bring nothing, so a predictive plan fits.

Објаснување на македонски (explanation in Macedonian)

Адаптивниот (агилен) пристап се избира кога барањата се неизвесни, промените се очекуваат и повратните информации од корисниците доаѓаат по секоја испорака. Само апликацијата за закажување има таква неизвесност во опсегот. Котлите, извештајот и преселбата имаат јасни барања и проверена процедура, па за нив одговара предиктивниот пристап.

Where this sits in PMI

Agile Practice Guide, section 2.1 (definable work versus high-uncertainty work) and section 3.1 (characteristics of project life cycles); PMBOK Guide 7th ed., Development Approach and Life Cycle performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0033)

Question 34 of 60

Agile · Task 1mediumone answer
Question 34. A logistics company is about to run its first adaptive project, with the team split between two offices. Before work starts, the project manager reviews the enterprise environmental factors and organisational process assets. Which condition would most facilitate the adaptive approach?

Pick one answer, then check.

Check the answer

Correct answer

  • AA product owner from the business who is available to the team throughout each iteration

The environmental factors and process assets that help an adaptive approach are those that speed up feedback and decisions: an engaged, available product owner, dedicated cross-functional team members, collaboration tooling for distributed teams and a culture that accepts change. Option A is the only condition that supplies them. Option C looks similar but the feedback cadence is wrong, option B describes a role acting against agile principles and option D belongs to the predictive toolbox.

Why, option by option - Question 34

  • A. Adaptive approaches depend on rapid decisions about value and priority. A product owner who is present every day answers questions, accepts work and reorders the backlog without waiting for a committee, and for a team split between offices that presence matters even more.

  • B. The scrum master is a servant leader who removes impediments and coaches the team; work is pulled by self-organising team members, not assigned. A scrum master who assigns work undermines the self-organisation the approach relies on.

  • C. A product owner exists, but quarterly feedback defeats the point of short iterations: the team would build for months without knowing whether the increment is right. Feedback has to arrive at least once per iteration.

  • D. These are organisational process assets that support a predictive life cycle. Phase gates and detailed schedule templates add ceremony an adaptive team does not use, so they do not facilitate the approach.

Објаснување на македонски (explanation in Macedonian)

Адаптивниот пристап најмногу го олеснува Сопственик на продуктот кој е достапен за тимот во текот на секоја итерација, зашто тој брзо одлучува за вредноста и приоритетите. Scrum Мастер не доделува задачи (опција B), квартална повратна информација е премногу ретка (опција C), а шаблоните и фазните контроли се средства за предиктивен пристап (опција D).

Where this sits in PMI

Agile Practice Guide, section 4.3 (team composition and agile roles) and section 6.2 (organisational culture); PMBOK Guide 7th ed., Team performance domain and Development Approach and Life Cycle performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0034)

Question 35 of 60

Agile · Task 2easyone answer
Question 35. A software team at a retail chain is planning its next two-week sprint. The product owner proposes the single objective the sprint should achieve, and the team then selects the backlog items that support it. What is this objective called?

Pick one answer, then check.

Check the answer

Correct answer

  • DSprint goal

In sprint planning the product owner proposes why the sprint is valuable, the team turns that into a sprint goal and then selects backlog items to deliver it. The product goal is the longer horizon, the sprint backlog is the output of the selection and the definition of done is the quality bar; only the sprint goal is the objective of the timebox.

Why, option by option - Question 35

  • A. The product goal is the longer-term objective the whole product backlog works toward, spanning many sprints. The objective proposed for one sprint is a step toward it, not the goal itself.

  • B. The sprint backlog is the set of items the team selects plus its plan for delivering them. It is built to serve the objective; it is not the objective.

  • C. The definition of done states the quality conditions every item must meet before it counts as complete. It applies to all sprints and does not describe what one particular sprint sets out to achieve.

  • D. The sprint goal is the one objective the sprint commits to, agreed in sprint planning. It gives the team a shared purpose and guides which items are selected and how scope is negotiated during the sprint.

Објаснување на македонски (explanation in Macedonian)

Целта што Сопственикот на продуктот ја предлага за еден Спринт, а тимот ја усвојува во Планирање на Спринтот, е Цел на Спринтот. Цел на Продуктот е долгорочна и опфаќа многу спринтови, Листа на планирани активности за Спринтот се избраните ставки, а Дефиниција за Завршено е условот за квалитет на секоја ставка.

Where this sits in PMI

Agile Practice Guide, section 5.2.6 (planning for iteration-based agile) and Annex A3 (Scrum); PMBOK Guide 7th ed., Planning performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0035)

Question 36 of 60

Agile · Task 2mediumone answer
Question 36. A project at an engineering firm was planned with a work breakdown structure before the sponsor agreed to switch to an adaptive approach. The project manager needs to turn the existing plan into something the team can plan iterations from. What should be done with the work packages?

Pick one answer, then check.

Check the answer

Correct answer

  • ADecompose them into user stories in a product backlog that the product owner orders by value

The work breakdown structure is not wasted when a project moves to an adaptive approach: its work packages become the raw material for a product backlog of features and user stories, which the product owner orders by value and the team decomposes further as it plans each iteration. What changes is the commitment, because only one iteration's worth is forecast at a time. A candidate who chose B recognised the backlog but missed that committing all scope to a single sprint backlog removes the adaptability the sponsor asked for.

Why, option by option - Question 36

  • A. Work packages describe deliverables, so they map naturally to features and user stories. Placed in a product backlog and ordered by value they become the input from which the team pulls work into each iteration and the product owner reprioritises as learning arrives.

  • B. Uses agile vocabulary but keeps the predictive idea of committing the entire scope up front. A sprint backlog holds only what the team forecasts for one timebox; the rest waits in the product backlog and can still change.

  • C. A Gantt chart of fixed activities is predictive tracking. The iteration review inspects a working increment with stakeholders; reporting percent complete against a schedule there mixes the two approaches without gaining any adaptability.

  • D. Phase gates are a predictive control that delivers nothing usable until the end of each phase. Adaptive planning works from a value-ordered backlog and delivers increments, not sequential gated phases.

Објаснување на македонски (explanation in Macedonian)

Работните пакети од структурата за поделба на работата се разложуваат во user stories во Листа на планирани активности за Продуктот, што Сопственикот на продуктот ја подредува според вредност. Само работата за една итерација се планира во Листа на планирани активности за Спринтот (опција B е погрешна), а Гантов дијаграм и фазните контроли се предиктивни алатки.

Where this sits in PMI

Agile Practice Guide, section 5.2.2 (backlog preparation) and 5.2.3 (backlog refinement); PMBOK Guide 7th ed., Planning performance domain and section 4.6 (hierarchy charts and backlog artifacts)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0036)

Question 37 of 60

Agile · Task 2mediumone answer
Question 37. A team at a bank delivers a lending feature set in two-week iterations, and the product owner reorders the backlog after every review. The sponsor asks whether the planned release date is still realistic. Which measure gives the best answer?

Pick one answer, then check.

Check the answer

Correct answer

  • DThe team's velocity trend against the remaining backlog on a burnup chart

Adaptive tracking forecasts from empirical delivery: completed work per iteration (velocity) extrapolated over the remaining backlog. A burnup chart shows both the completed line and the scope line, so a growing backlog is visible rather than hidden. Predictive measures such as critical-path variance depend on a fixed activity plan that changes every iteration here, remaining points alone lack the rate, and hours logged measure effort rather than progress.

Why, option by option - Question 37

  • A. Critical-path schedule variance assumes a fixed network of activities agreed in advance. With the backlog reordered every iteration there is no stable activity network to measure against, so the variance would describe a plan that no longer exists.

  • B. Remaining size is half the picture. Without the rate at which the team finishes points it cannot say when the backlog will be exhausted, so it does not answer whether the date holds.

  • C. Effort spent is an input measure; it says nothing about how much accepted, working product exists or how much remains. Adaptive tracking measures completed value, not hours consumed.

  • D. Velocity is the amount of work the team actually completes per iteration. Plotted with the remaining scope on a burnup chart it projects when the backlog will be done and shows scope changes as they happen, which is what the sponsor's question needs.

Објаснување на македонски (explanation in Macedonian)

Во адаптивен проект напредокот се следи според завршената работа по итерација (velocity) споредена со преостанатата Листа на планирани активности за Продуктот, најчесто на burnup chart. Критичниот пат претпоставува фиксен план што овде се менува секоја итерација; преостанатите story points без стапка на завршување не даваат прогноза, а потрошените часови мерат напор, а не испорачана вредност.

Where this sits in PMI

Agile Practice Guide, section 5.4 (measurements in agile projects); PMBOK Guide 7th ed., Measurement performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0037)

Question 38 of 60

Agile · Task 3easymultiple answers
Question 38. The project management office of a government agency is drafting a checklist of the artifacts it expects to see on an adaptive project. Which two artifacts belong on the list? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • AProduct backlog
  • DBurndown chart

Adaptive artifacts are the ones that support planning one timebox at a time and making progress visible: backlogs, increments, burn charts, kanban boards, the definition of done and information radiators. Network diagrams, traceability matrices and phase gates all assume requirements and sequence fixed in advance, which is the predictive model.

Why, option by option - Question 38

  • A. The ordered list of everything the product may need is the central planning artifact of an adaptive project. Every iteration is planned from it and it changes as the product owner learns.

  • B. A schedule network diagram fixes activity sequences and float for the whole project in advance. It belongs to predictive scheduling; adaptive teams plan one iteration at a time from the backlog.

  • C. A traceability matrix links a fixed set of requirements to design, build and test through a predictive project. In an adaptive project requirements live as backlog items with acceptance criteria and are expected to change, so the matrix is not a standard artifact.

  • D. A burndown chart shows the work remaining in an iteration or release against time. It is one of the standard visual artifacts adaptive teams use to track progress and keep it visible.

  • E. Phase gates close one phase before the next begins, which is a predictive life-cycle control. Adaptive projects replace them with iteration reviews of a working increment.

Објаснување на македонски (explanation in Macedonian)

Артефакти на адаптивен проект се Листа на планирани активности за Продуктот и burndown chart, зашто поддржуваат планирање на една итерација и видлив напредок. Мрежен дијаграм со критичен пат, матрица за следливост на барањата и фазните контроли претпоставуваат однапред фиксирани барања и редослед, што е предиктивен модел.

Where this sits in PMI

PMBOK Guide 7th ed., section 4.6 (artifacts, including backlogs and burn charts); Agile Practice Guide, section 5.4 (measurements in agile projects) and section 5.2 (common agile practices)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0038)

Question 39 of 60

Agile · Task 3mediumone answer
Question 39. On a healthcare-records project a developer finishes a user story that satisfies all the acceptance criteria the product owner wrote, but the integration test the team agreed to run on every story has not been executed. The team does not count the story as finished. Which project control is the team applying?

Pick one answer, then check.

Check the answer

Correct answer

  • CDefinition of done

Two controls decide whether a story is complete: the acceptance criteria written for that story, and the definition of done that applies to every story. The story passed the first and failed the second, so the definition of done is the control at work. A candidate who chose A read "acceptance criteria" in the stem and stopped; the stem states they were met, which is the clue that a different, team-level control is being applied.

Why, option by option - Question 39

  • A. Acceptance criteria are the conditions specific to one story that the product owner uses to accept it, and the stem says they were satisfied. They are necessary but not sufficient; the story fails a team-wide condition instead.

  • B. The sprint review is the event where the increment is inspected with stakeholders. It is a meeting, not the rule that decides whether an item counts as complete before it reaches that meeting.

  • C. The definition of done is the shared list of quality conditions that every item must meet regardless of its individual acceptance criteria. An untested story does not meet it, so it cannot be counted as complete or included in the increment.

  • D. The sprint goal is the objective the sprint commits to. It shapes which items are selected, but it does not define the quality state an item must reach to be counted as complete.

Објаснување на македонски (explanation in Macedonian)

Приказната ги исполнува acceptance criteria на Сопственикот на продуктот, но не и заедничкиот услов на тимот дека секоја приказна поминува интеграциски тест. Тој заеднички услов е Дефиниција за Завршено, што важи за секоја ставка. Преглед на Спринтот е настан, а Цел на Спринтот е целта на спринтот, а не услов за квалитет.

Where this sits in PMI

Agile Practice Guide, section 5.2.7 (execution practices, testing at all levels) and Annex A3 (Scrum); PMBOK Guide 7th ed., Delivery performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0039)

Question 40 of 60

Agile · Task 4easyone answer
Question 40. At the end of every sprint a Scrum team at a telecom firm meets with its stakeholders to inspect the increment that was built and to adjust the product backlog based on what they learn. Which Scrum event is this?

Pick one answer, then check.

Check the answer

Correct answer

  • BSprint review

Scrum has four events inside the sprint container, each with a distinct purpose: planning (what to build), the daily scrum (team synchronisation), the review (inspect the product with stakeholders and adapt the backlog) and the retrospective (inspect the process). Stakeholders and the product backlog point to the review; the retrospective is the common confusion, but it looks at the team's way of working, not the increment.

Why, option by option - Question 40

  • A. Sprint planning opens the sprint: the team sets the sprint goal and selects backlog items. It looks forward at what to build, not back at what was built.

  • B. The sprint review closes the sprint's work by inspecting the increment with stakeholders and adapting the product backlog; it is the feedback event that keeps the product on track.

  • C. The retrospective inspects how the team worked, its process, tools and relationships, and plans improvements. It is held by the Scrum team without stakeholders and does not examine the product increment.

  • D. The daily scrum is a short event for the developers to inspect progress toward the sprint goal and plan the next day. It is internal to the team and happens every day, not at the end of the sprint.

Објаснување на македонски (explanation in Macedonian)

Настанот во кој Scrum Тимот со засегнатите страни го проверува Инкрементот и ја прилагодува Листата на планирани активности за Продуктот е Преглед на Спринтот. Ретроспектива на Спринтот го разгледува начинот на работа на тимот, Планирање на Спринтот гледа напред, а Дневен Scrum е краток дневен настан на Девелоперите.

Where this sits in PMI

Agile Practice Guide, section 5.2.5 (demonstrations and reviews) and Annex A3 (Scrum); PMBOK Guide 7th ed., Delivery performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0040)

Question 41 of 60

Agile · Task 4mediummultiple answers
Question 41. A software team at an insurance company says it follows Extreme Programming (XP). Which two practices would a project manager expect to find in the team's way of working? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • BTwo developers writing code together at one workstation
  • EWriting an automated test before the code that makes it pass

XP is defined by its engineering practices: pair programming, test-driven development, continuous integration, refactoring, simple design and collective code ownership. The distractors are the signature practices of neighbouring frameworks: WIP limits (Kanban), program increment planning (SAFe) and the sprint review (Scrum). A team can combine them, but only B and E identify XP itself.

Why, option by option - Question 41

  • A. WIP limits are the defining practice of the Kanban method, used to expose bottlenecks and improve flow. They are not part of XP's practice set, although a team may choose to add them.

  • B. Pair programming is a core XP practice: continuous review as the code is written, shared knowledge across the team and fewer defects.

  • C. Program increment planning is a component of the Scaled Agile Framework (SAFe), which coordinates many teams on a shared cadence. XP is a single-team method and has no such event.

  • D. The sprint review is a Scrum event. XP works in short iterations too, but the sprint and its formal review are Scrum's vocabulary, not XP's.

  • E. Test-driven development is a core XP engineering practice: the test defines the behaviour first, then the code is written to satisfy it and refactored.

Објаснување на македонски (explanation in Macedonian)

Практиките на Extreme Programming (XP) се pair programming (двајца Девелопери на една работна станица) и test-driven development (прво тест, па код). WIP лимитот припаѓа на Kanban, program increment planning на SAFe, а Преглед на Спринтот е настан од Scrum.

Where this sits in PMI

Agile Practice Guide, Annex A3.3 (eXtreme Programming) and section 5.2.7 (execution practices that help teams deliver value); PMBOK Guide 7th ed., Development Approach and Life Cycle performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0041)

Question 42 of 60

Agile · Task 4hardone answer
Question 42. A Scrum team at an energy utility also supports a live billing system, and urgent production fixes arrive almost daily. The sprint goal has been missed in each of the last four sprints, and the team wants to change how it manages its work. Which change fits the situation best?

Pick one answer, then check.

Check the answer

Correct answer

  • CMove to a flow-based board with work-in-progress limits and pull each fix when capacity frees

The Agile Practice Guide describes flow-based approaches as the fit for work that arrives continuously and cannot be forecast for a timebox, and iteration-based approaches for work that can be committed for a sprint. When a team's sprints are broken daily by legitimate urgent work, the method, not the team, is the mismatch. Options A and D are correct Scrum mechanics that do not resolve it, and B violates the scrum master's role. A candidate torn between A and C should ask whether the interruptions would stop with a shorter sprint; they would not.

Why, option by option - Question 42

  • A. A shorter timebox is a legitimate Scrum adjustment, but the fixes arrive daily, so even a one-week commitment would still be broken. It treats the symptom by planning more often rather than matching the method to interrupt-driven work.

  • B. The scrum master is a servant leader who coaches the team and removes impediments; assigning work is not the role. It also leaves the mismatch between fixed sprint commitments and unpredictable arrivals untouched.

  • C. Kanban's flow model suits work that arrives unpredictably: there is no fixed-scope timebox to break, WIP limits keep the team from overloading, and each item is pulled when someone is free, so fixes and planned items share one visible flow.

  • D. Protecting the sprint goal is Scrum by the book, and the product owner does decide priority, but production fixes on a live billing system cannot wait for the next timebox. The rule is being applied against the value it exists to protect.

Објаснување на македонски (explanation in Macedonian)

Кога работата пристигнува непредвидливо и секој ден го нарушува Спринтот, Scrum со фиксна обврска за временски ограничен период не одговара; проток по Kanban со WIP лимити и повлекување на ставки според слободен капацитет одговара. Пократок Спринт не ги запира прекините, Scrum Мастер не доделува задачи, а одложувањето на итни поправки на производствен систем ја жртвува вредноста што Целта на Спринтот треба да ја штити.

Where this sits in PMI

Agile Practice Guide, section 3.1.4 (characteristics of agile life cycles: iteration-based and flow-based agile) and section 3.2 (mixing agile approaches), Annex A3.4 (Kanban Method) and A3.6 (Scrumban); PMBOK Guide 7th ed., Development Approach and Life Cycle performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0042)

Question 43 of 60

Agile · Task 5easyone answer
Question 43. An iteration at a retail-software company is about to end and a newly joined team member asks how the team will judge whether the iteration succeeded. Which criterion is best?

Pick one answer, then check.

Check the answer

Correct answer

  • DA working increment that meets the sprint goal is accepted by the product owner

The success criterion of an adaptive iteration is outcome-based: an increment that meets the definition of done, achieves the sprint goal and is accepted by the product owner. Velocity, items started and hours consumed are activity or capacity measures; none confirms that value was delivered. A candidate who chose A confused a forecasting metric with a success criterion.

Why, option by option - Question 43

  • A. Velocity is a planning measure for forecasting how much the team can take on. It varies naturally, and a rising velocity says nothing about whether what was built is usable or valuable.

  • B. Started work is partially done work. Adaptive approaches count only completed, accepted items as progress; ten half-finished stories deliver no value and cannot be inspected at the review.

  • C. Spending the budgeted effort is an input measure inherited from predictive tracking. It measures consumption, not the outcome the iteration set out to achieve.

  • D. Success in adaptive delivery is a done, potentially usable increment that achieves the objective the team committed to, confirmed by the product owner's acceptance at the review. That is the criterion the iteration was planned against.

Објаснување на македонски (explanation in Macedonian)

Итерацијата е успешна кога работен Инкремент што ја исполнува Целта на Спринтот е прифатен од Сопственикот на продуктот. Velocity е мерка за планирање, започнатите ставки не се испорачана вредност, а потрошените часови мерат напор, а не резултат.

Where this sits in PMI

Agile Practice Guide, section 5.2.8 (how iterations and increments help deliver working product) and section 5.4.1 (agile teams measure results); PMBOK Guide 7th ed., Delivery performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0043)

Question 44 of 60

Agile · Task 5hardone answer
Question 44. Midway through a sprint at a software company, the head of finance asks a developer directly to add a quarter-end report to the current sprint because it is urgent. The developer estimates it at two days. What should the developer do?

Pick one answer, then check.

Check the answer

Correct answer

  • BDirect the request to the product owner, who decides where it goes in the product backlog

In an adaptive project all requests flow through the product owner, who owns the order of the product backlog; the developers decide how much they can take on and the scrum master facilitates but decides neither. Option D is right about the mechanism (a swap) and wrong about the role, which is what makes the item hard. Option C is the predictive change-control reflex, and option A ignores prioritisation altogether.

Why, option by option - Question 44

  • A. Seniority is not priority. Taking work directly from a stakeholder bypasses the product owner, breaks the sprint's forecast and invites every stakeholder to route requests to whichever developer they know.

  • B. The product owner is the single point of prioritisation and orders the backlog by value; the developer's job is to route the request there. If the product owner judges it more valuable than current sprint work, the sprint scope can be renegotiated with the developers.

  • C. A formal change request through a change control board is the predictive reflex. In an adaptive project change is absorbed through the backlog, not a board; the product owner decides, quickly, without a gate.

  • D. Swapping an item is a legitimate way to adjust a sprint, which makes this tempting, but the scrum master neither orders the backlog nor decides sprint scope. That decision belongs to the product owner with the developers; asking the scrum master to make it misplaces the role.

Објаснување на македонски (explanation in Macedonian)

Секое ново барање оди кај Сопственикот на продуктот, кој ја подредува Листата на планирани активности за Продуктот според вредност и одлучува дали ставката влегува во тековниот Спринт во договор со Девелоперите. Scrum Мастер не одлучува за опсегот (опција D), формалната контрола на промени е предиктивен рефлекс (опција C), а прифаќањето на барањето директно ја заобиколува приоритизацијата (опција A).

Where this sits in PMI

Agile Practice Guide, section 4.3.2 (agile roles) and section 5.2.3 (backlog refinement); PMBOK Guide 7th ed., Stakeholder performance domain and Planning performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0044)

Question 45 of 60

Business analysis · Task 1mediumone answer
Question 45. A business analyst at a regional bank has designed a shorter loan-approval process. The supervisor who runs the approval desk every day agrees with the redesign and offers to sign it off, but the analyst says a different sign-off is needed before the process itself can be changed. Whose approval is the analyst waiting for?

Pick one answer, then check.

Check the answer

Correct answer

  • CThe process owner

The PMI business analysis guides separate the person who operates a process (process manager) from the person accountable for how it is designed and performs (process owner). The supervisor in the stem manages the desk, so their agreement is stakeholder input, not authorisation. A candidate who chose the process manager confused daily operation with ownership; a candidate who chose product owner or product manager mixed product roles into a process decision.

Why, option by option - Question 45

  • A. The process manager runs the process day to day, allocates the people and watches its throughput; that is the supervisor in the stem. Operating a process is not the same as being accountable for its design, so this signature is not the one that authorises a redesign.

  • B. A product manager is accountable for a product's strategy, market fit and roadmap. Loan approval is an internal process, not a product line, so this role has no authority over how the process is designed.

  • C. The process owner is accountable for the end-to-end design and performance of the process and is the role that approves changes to it. The supervisor's agreement is valuable input, but the redesign is only authorised when the owner signs it off.

  • D. A product owner orders a product backlog and decides what an adaptive team builds next. The stem is about who can authorise a change to an operating process, which is the process owner's accountability rather than a backlog decision.

Објаснување на македонски (explanation in Macedonian)

Process owner е засегнатата страна одговорна за дизајнот и резултатите на процесот од почеток до крај и токму таа ја одобрува промената на процесот. Супервизорот што го води процесот секојдневно е process manager: неговата согласност е вредна, но не е одобрување. Product manager и Сопственикот на продуктот се улоги врзани за производ, а не за интерен процес.

Where this sits in PMI

PMI Guide to Business Analysis, Stakeholder Engagement knowledge area (stakeholder roles and their accountabilities); Business Analysis for Practitioners: A Practice Guide, 2nd ed., stakeholder engagement chapter (process owner and process manager)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0045)

Question 46 of 60

Business analysis · Task 1mediumone answer
Question 46. A software firm built an invoicing feature from requirements gathered only from its sales department. At user acceptance testing, the finance department rejects the feature because it ignores their month-end closing rules, which nobody had asked about. Which activity, done at the start, would most likely have prevented this?

Pick one answer, then check.

Check the answer

Correct answer

  • AIdentifying and analysing the stakeholders affected by the solution

The reason stakeholders are identified and analysed before elicitation is that a stakeholder who is missed contributes no requirements and later withholds acceptance, which is exactly what finance did. Prioritisation, traceability and prototyping all work on requirements that already exist; none of them discovers a group nobody thought to ask. A candidate who chose traceability confused proving coverage of known requirements with completeness of the requirement set.

Why, option by option - Question 46

  • A. Finance was affected by the invoicing feature but was never identified, so their needs never entered the requirements. Stakeholder identification and analysis exists precisely to find every group whose needs, influence or acceptance the solution depends on before elicitation begins.

  • B. Prioritisation orders the requirements that have already been captured. It cannot surface a need from a department that was never consulted, so ranking the sales requirements more carefully would not have added the finance rules.

  • C. Traceability shows that each captured requirement is covered by design and testing. The finance requirement was never captured, so a complete matrix would still have shown a fully tested feature that was wrong for finance.

  • D. Prototyping is a strong elicitation and confirmation technique, but a prototype reviewed only with sales would confirm the sales view. The gap was in who was consulted, not in how well their needs were understood.

Објаснување на македонски (explanation in Macedonian)

Финансиите биле засегната страна на решението, но никој не ги идентификувал, па нивните барања воопшто не биле собрани. Анализа на учесниците на почетокот го открива секој што има потреба или влијание врз решението. Приоритизацијата, traceability matrix и прототипот работат само врз веќе собрани барања и не можат да откријат изоставена група.

Where this sits in PMI

PMI Guide to Business Analysis, Stakeholder Engagement knowledge area (identify stakeholders, conduct stakeholder analysis); PMBOK Guide 7th ed., Stakeholder performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0046)

Question 47 of 60

Business analysis · Task 1easyone answer
Question 47. A regional airport authority is building a baggage-tracking system. The business analyst lists the civil aviation regulator, the outsourced software vendor's analyst who sits with the team every day, the airport's operations manager and the passengers who will use the tracking app. Which of these is an internal stakeholder?

Pick one answer, then check.

Check the answer

Correct answer

  • DThe airport's operations manager

Internal and external are decided by organisational membership, not by proximity or influence. The regulator, the supplier's analyst and the passengers all sit outside the airport authority; only the operations manager is inside it. A candidate who chose the vendor's analyst let daily co-location override the contractual boundary that defines an external role.

Why, option by option - Question 47

  • A. A regulator imposes requirements from outside the organisation and is a classic external stakeholder, however much influence it has over the solution.

  • B. Co-location and daily contact are tempting cues, but the analyst is employed by a supplier under contract. Where a person sits does not change whose organisation they belong to; a supplier's staff are external stakeholders.

  • C. End customers are among the most important stakeholders, but they are outside the organisation delivering the solution and are therefore external.

  • D. The operations manager is employed by the airport authority, the organisation sponsoring and delivering the project. Internal stakeholders are those inside that organisation, regardless of how often the analyst meets them.

Објаснување на македонски (explanation in Macedonian)

Дали една засегната страна е внатрешна или надворешна зависи од тоа на која организација ѝ припаѓа, а не од тоа колку често тимот се среќава со неа. Регулаторот, аналитичарот на изведувачот и патниците се надворешни; само менаџерот за операции е вработен во аеродромот и е внатрешна засегната страна.

Where this sits in PMI

PMI Guide to Business Analysis, Stakeholder Engagement knowledge area (internal and external stakeholders); PMBOK Guide 7th ed., Stakeholder performance domain

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0047)

Question 48 of 60

Business analysis · Task 2mediumone answer
Question 48. A business analyst at a government ministry has analysed two solution options for a citizen-records system. The state secretary and two directors can give the analyst thirty minutes and must leave the meeting with a funding decision. Which communication approach fits this audience and purpose best?

Pick one answer, then check.

Check the answer

Correct answer

  • BA short options briefing with a recommendation and time for questions

Choosing a communication channel starts from the audience and the purpose: senior decision makers, little time, a decision required. A presentation with a recommendation and space for questions delivers a synthesis and lets the audience test it, which a report or dashboard cannot do and a workshop is too long for. A candidate who chose the status report picked a familiar channel for periodic information rather than one built for reaching a decision.

Why, option by option - Question 48

  • A. A status report is the right channel for periodic progress information, but it is one-way and does not support a discussion that must end in a decision. Sending it beforehand may help, yet it does not use the thirty minutes to reach the decision.

  • B. A decision-focused presentation suits a senior audience with little time: it frames the two options, states the trade-offs and recommendation, and leaves room for the questions the decision makers need answered before they commit. It matches both the audience and the purpose.

  • C. A workshop is the tool for building consensus or eliciting requirements with many contributors. The options are already analysed and the audience has thirty minutes, so a half-day co-creation session fits neither the purpose nor the time available.

  • D. A dashboard supports ongoing monitoring by people who track detail over time. Senior decision makers choosing between two funded options need a synthesis and a recommendation, not requirement-level status.

Објаснување на македонски (explanation in Macedonian)

Каналот се избира според публиката и целта: високи носители на одлуки, малку време, потребна одлука. Кратка презентација со препорака и време за прашања го дава она што им треба. Извештај за проектен статус е еднонасочен, работилницата е предолга, а dashboard е за следење детали, не за одлучување.

Where this sits in PMI

PMI Guide to Business Analysis, Stakeholder Engagement knowledge area (communication planning and channels); PMBOK Guide 7th ed., Stakeholder performance domain (communication methods)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0048)

Question 49 of 60

Business analysis · Task 2mediumone answer
Question 49. At a furniture manufacturer, the plant supervisors own the requirements for a new shift-scheduling feature and the software team builds it. The business analyst notices that the team has started building a report on its own reading of a requirement the supervisors wrote ambiguously, and the supervisors are unaware. What should the analyst do first?

Pick one answer, then check.

Check the answer

Correct answer

  • CConfirm the intended meaning with the supervisors and relay it to the team

A business analyst communicates between the requirement owners and the delivery team so that both hold the same understanding of each requirement; when that understanding diverges, the analyst closes the gap at once, with the people who own the need. A candidate who chose to wait for the review confused confirming a finished increment with keeping shared understanding during the work; a candidate who chose a change request treated an ambiguity as a scope change.

Why, option by option - Question 49

  • A. Waiting until the review means the team may build for days on an interpretation that the requirement owners never held. The review is for confirming a completed increment, not for discovering that the two groups understood a requirement differently.

  • B. Nothing has changed yet: the requirement is ambiguous, not altered. Change control comes into play only if clarification reveals that the agreed scope must actually move, and even then after the meaning has been confirmed.

  • C. The analyst's central communication role is to keep the people who own the need and the people who build the solution working from the same understanding. Clarifying now, at the source, and passing the answer to the team prevents rework and is why the analyst sits between the two groups.

  • D. Reserving time for rework accepts the misunderstanding rather than removing it. The analyst can eliminate the cause with a short clarification, which is the better use of the moment than planning around the consequence.

Објаснување на македонски (explanation in Macedonian)

Аналитичарот стои меѓу оние што го поседуваат барањето и тимот што го гради, за двете страни да го разбираат исто. Кога разбирањата се разидуваат, прво се потврдува значењето кај супервизорите и одговорот се пренесува на тимот. Чекање до прегледот носи преработка; контрола на промени се применува само ако опсегот навистина се менува.

Where this sits in PMI

PMI Guide to Business Analysis, Stakeholder Engagement and Analysis knowledge areas (communicating requirements, confirming understanding); Business Analysis for Practitioners: A Practice Guide, 2nd ed., analysis chapter (validating and communicating requirements)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0049)

Question 50 of 60

Business analysis · Task 3easyone answer
Question 50. The logistics team of a humanitarian NGO wants to see how a donated shipment moves from arrival at the warehouse to distribution in the field, including every hand-off between departments, so that the delays can be found. Which requirements tool fits this need best?

Pick one answer, then check.

Check the answer

Correct answer

  • BA process model

Matching a tool to the scenario: an end-to-end flow with hand-offs and waiting points is what a process model is built to show. User stories and use cases describe needs and system interactions, and a prototype shows a future solution. A candidate who chose the use case confused a single actor's interaction with a system for a cross-departmental flow of work.

Why, option by option - Question 50

  • A. A user story captures a single need from one role's point of view in a sentence or two. It is deliberately small and does not show a sequence of hand-offs across departments.

  • B. A process model (a flow diagram with swimlanes) shows the steps, decisions and hand-offs between roles from the start of a process to its end. It is the tool for seeing where work waits, which is exactly what the team wants.

  • C. A use case describes how an actor interacts with a system to reach a goal, step by step. It centres on one interaction with the solution, not on how work flows between several departments.

  • D. A prototype makes a proposed solution tangible so stakeholders can react to it. The team is trying to understand the current process, not to try out a future screen or product.

Објаснување на македонски (explanation in Macedonian)

Тек на работа од почеток до крај, со предавања меѓу одделенијата, најдобро се прикажува со process model. User story опишува една потреба на една улога, use case опишува како актер комуницира со системот, а прототип прикажува идно решение, не постоечки процес.

Where this sits in PMI

PMI Guide to Business Analysis, Analysis knowledge area (process models, use cases, user stories); Business Analysis for Practitioners: A Practice Guide, 2nd ed., analysis chapter (modelling techniques)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0050)

Question 51 of 60

Business analysis · Task 3mediummultiple answers
Question 51. An insurance company is replacing a claims system used by nine hundred clerks in forty branches. Within a month the business analyst must learn how the clerks actually handle a claim today and how widely a proposed change to the approval step would be accepted across the branches. Which two elicitation techniques best fit this situation? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • AObserving clerks handling claims at a sample of branches
  • DSurveying the clerks in all forty branches

Two questions, two techniques: observation for how the work is actually done (people cannot reliably describe their own habits) and a survey for a broad, dispersed population whose acceptance must be measured in a short time. The other options use legitimate techniques with the wrong participants, which is the trap: the technique is only as good as who it is applied to. A candidate who chose the sponsor interview mistook the sponsor's authority for knowledge of branch practice.

Why, option by option - Question 51

  • A. Observation shows what people actually do, including the workarounds they would not think to describe. It is the technique for learning how a process really runs today, and a sample of branches makes it feasible within the month.

  • B. An interview is right for depth with one person, but the sponsor is not the one performing the work and cannot say how forty branches would receive the change. It answers neither of the two questions the analyst has.

  • C. Brainstorming generates ideas for how something could be done; it does not produce evidence of how nine hundred clerks handle a claim today, and a single head-office group cannot show how forty branches would receive the change.

  • D. A survey reaches a large, dispersed population quickly and gives a measurable picture of how a proposed change is received. For nine hundred people in forty locations within a month, it is the technique that scales.

  • E. A focus group gathers the views of a selected group of stakeholders, but the developers neither perform the claims process nor decide whether the approval change is acceptable in the branches. The wrong participants make the technique miss the target.

Објаснување на македонски (explanation in Macedonian)

Две прашања бараат две техники: набљудување на службениците за да се види како навистина работат, и анкета за да се измери прифаќањето кај 900 луѓе во 40 филијали за еден месец. Другите опции користат вистински техники, но на погрешно место: спонзорот и девелоперите не го извршуваат процесот, а brainstorming со една група во централата дава идеи, не докази.

Where this sits in PMI

PMI Guide to Business Analysis, Elicitation knowledge area (observation, surveys and questionnaires, interviews, focus groups); Business Analysis for Practitioners: A Practice Guide, 2nd ed., elicitation chapter (selecting techniques)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0051)

Question 52 of 60

Business analysis · Task 3easyone answer
Question 52. On a road-construction project, the business analyst maintains a table in which each requirement is linked backward to the business objective it serves and forward to the design element and the test that covers it. What is the primary purpose of this artefact?

Pick one answer, then check.

Check the answer

Correct answer

  • DTo follow each requirement from its origin to the deliverable that satisfies it

The artefact described is a requirements traceability matrix, whose purpose is to connect each requirement backward to its origin and forward to what satisfies and verifies it, so nothing is lost and nothing unrequested is built. Prioritisation, acceptance criteria and estimates are neighbouring artefacts that a candidate may associate with the same table without being its purpose.

Why, option by option - Question 52

  • A. Ranking is the job of prioritisation techniques such as MoSCoW or multivoting. The table in the stem records relationships, not the relative importance of one requirement over another.

  • B. Those conditions are acceptance criteria, written with the requirement or user story. The linking table may reference the test that checks them, but it does not define them.

  • C. Effort belongs to estimating and to the schedule or backlog, not to the linking table. Knowing where a requirement came from and what covers it says nothing about how long it takes.

  • D. That is the requirements traceability matrix: it shows that every requirement has a source and a covering deliverable and test, exposes orphans and gaps, and supports impact analysis when something changes.

Објаснување на македонски (explanation in Macedonian)

Опишаниот артефакт е requirements traceability matrix: секое барање се следи назад до целта од која потекнува и напред до испораката и тестот што го покриваат. Приоритизацијата, acceptance criteria и проценката на напор се соседни артефакти, но не се негова цел.

Where this sits in PMI

PMI Guide to Business Analysis, Traceability and Monitoring knowledge area (requirements traceability matrix); Process Groups: A Practice Guide, Collect Requirements (traceability matrix)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0052)

Question 53 of 60

Business analysis · Task 3easyone answer
Question 53. A university's student-portal team keeps a single ranked list of features, fixes and technical work. The product owner reorders it as priorities shift and the business analyst refines the top items with the team before each iteration. What does this artefact provide?

Pick one answer, then check.

Check the answer

Correct answer

  • AThe one source of work the team pulls from, reshaped as understanding grows

The artefact is a product backlog: a single, ordered, continually refined list of candidate work owned by the product owner. Its defining features are that it is emergent and ordered, not baselined, and that it holds the work rather than tracing or scheduling it. A candidate who chose the release view confused the pool of work with the plan for delivering it.

Why, option by option - Question 53

  • A. That is the product backlog: an emergent, ordered inventory of everything that may be built, owned by the product owner, with the items nearest the top refined to a ready state and the rest kept deliberately coarse.

  • B. A scope baseline belongs to the predictive approach and is changed through change control. The list in the stem is reordered freely as priorities shift, which is the opposite of a baseline.

  • C. That is the traceability matrix. The backlog may reference acceptance criteria, but its job is to hold and order the work, not to prove coverage between requirements and tests.

  • D. That is a release plan or product roadmap. The backlog is the ordered pool the releases draw from; it does not itself assign items to dates or releases.

Објаснување на македонски (explanation in Macedonian)

Артефактот е Листа на планирани активности за Продуктот: една подредена листа на сета можна работа, во сопственост на Сопственикот на продуктот, која постојано се прилагодува. Не е основна линија на опсегот, не е traceability matrix и не е план за изданија, туку изворот од кој тие црпат.

Where this sits in PMI

Agile Practice Guide, section on backlog preparation and refinement; PMI Guide to Business Analysis, Analysis knowledge area (product backlog as a requirements artefact)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0053)

Question 54 of 60

Business analysis · Task 4easyone answer
Question 54. The product manager at a telecom operator shares a one-page view with the executive team: four quarters across the top, three themes such as self-service billing and network coverage, and what each theme is meant to achieve for customers. What does this artifact communicate?

Pick one answer, then check.

Check the answer

Correct answer

  • CThe strategic direction and intended outcomes across time

A product roadmap is a high-level communication of direction: themes, outcomes and approximate timeframes that let stakeholders see where the product is going and judge releases against that intent. It is neither a schedule of commitments nor a scope baseline nor a task network. A candidate who chose the delivery-date option treated the quarters on the page as promises rather than as a horizon.

Why, option by option - Question 54

  • A. A roadmap places themes in broad timeframes, not features on dates. Reading it as a set of date commitments is the most common misuse and the reason product managers stress that it will change.

  • B. A scope baseline is a controlled, detailed description of what one release contains. The roadmap sits above releases and stays at the level of themes and outcomes.

  • C. That is what a product roadmap is for: it aligns stakeholders on where the product is heading, why, and roughly when, so that releases and backlog decisions can be judged against a shared intent.

  • D. A dependency sequence is what a network diagram and the critical path show. The roadmap does not model tasks or their dependencies; it communicates intent at a much higher level.

Објаснување на македонски (explanation in Macedonian)

Product roadmap ја соопштува стратешката насока: теми, очекувани резултати и приближни временски рамки, за сите засегнати страни да гледаат кон иста цел. Не е временски распоред со ветени датуми, не е основна линија на опсегот и не е мрежен дијаграм на задачи.

Where this sits in PMI

PMI Guide to Business Analysis, Needs Assessment knowledge area (Facilitate Product Roadmap Development); Business Analysis for Practitioners 2nd ed., product roadmap and release planning

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0054)

Question 55 of 60

Business analysis · Task 4mediumone answer
Question 55. An online grocery retailer is planning three releases of its shopping app. The first release must go live before the end of the quarter and stay as small as possible; customer login is already scheduled for the second release. Which backlog item belongs in the first release?

Pick one answer, then check.

Check the answer

Correct answer

  • BA cookie-consent banner that the law requires from the start of next quarter

Assigning components to releases weighs value, dependency, risk and timing together, and a minimal first release keeps only what must be there to go live safely. The banner is the one item that is obligatory by the launch date and free of dependencies; the loyalty balance is blocked by login, the export has no customer value and the wish list is unsized. A candidate who chose the wish list ranked desirability above the release constraints that decide readiness.

Why, option by option - Question 55

  • A. It has clear customer value, but it depends on login, which arrives only in release two. An item cannot ship before the component it depends on, whatever its value.

  • B. The release goes live before the quarter ends and the banner is a legal obligation from the day after; leaving it out would make the launch non-compliant. It has no dependency on login and is small, so it fits a minimal first release on every criterion: obligation, risk, dependency and size.

  • C. Sponsor interest is real, but the item serves an internal reporting need with no customer value and no time constraint. It can wait for a later release without cost, which is what a minimal first release requires.

  • D. Highest desirability is tempting, but an unestimated item cannot be committed to a fixed-date release and is not needed for compliance or for the app to work. It is a strong candidate for release two or three once sized.

Објаснување на македонски (explanation in Macedonian)

Распределбата по изданија ги мери заедно вредноста, зависностите, ризикот и рокот. Банерот за согласност е законска обврска од почетокот на следниот квартал, а изданието оди во живо пред крајот на овој, и нема зависност од најавата, па мора во првото издание. Бодовите за лојалност зависат од најавата, извозот за маркетинг нема вредност за клиентите, а wish-list нема проценка.

Where this sits in PMI

PMI Guide to Business Analysis, Needs Assessment knowledge area (Facilitate Product Roadmap Development) and Analysis knowledge area (Prioritize Requirements and Other Product Information); Agile Practice Guide, section on release planning

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0055)

Question 56 of 60

Business analysis · Task 5mediumone answer
Question 56. On an adaptive project delivering a municipal services app, the product owner has ordered the backlog for the next iteration. The business analyst's value analysis shows that an item ranked lower would deliver more benefit to citizens than the item ranked first. What should the analyst do?

Pick one answer, then check.

Check the answer

Correct answer

  • DPresent the analysis to the product owner and support whatever ordering they decide

In adaptive approaches the business analyst works alongside the product owner, refining items and supplying analysis, but the product owner orders the backlog. Options A and C both act on the analyst's conclusion without the product owner deciding, and B escalates before the accountable person has even been consulted. A candidate who chose to reorder confused analysing value with owning the decision about it.

Why, option by option - Question 56

  • A. The analyst elicits and analyses requirements, but ordering the product backlog is the product owner's accountability. Changing the order unilaterally oversteps the role even when the analysis is sound.

  • B. Escalation is for issues the accountable role cannot resolve. The product owner has not yet seen the analysis, so nothing has been left unresolved; escalating first would bypass the person whose decision it is.

  • C. Handing the choice to the developers moves a value decision away from the product owner, and detailing both items in full contradicts just-in-time refinement. The developers decide how to build, not which item carries more value.

  • D. In an adaptive approach the analyst informs the product owner's decisions with evidence and refinement, while the ordering itself stays with the product owner. Sharing the value analysis respects the role and gives the decision maker what they need.

Објаснување на македонски (explanation in Macedonian)

Во агилен пристап аналитичарот му помага на Сопственикот на продуктот со анализа и прилагодување на ставките, но подредувањето на Листата на планирани активности за Продуктот останува кај Сопственикот. Затоа анализата се презентира и одлуката се поддржува. Самостојно преуредување, ескалација пред разговор или префрлање на изборот на Девелоперите ја заобиколуваат улогата што одлучува.

Where this sits in PMI

Agile Practice Guide, section on team roles (product owner) and backlog refinement; PMI Guide to Business Analysis, Analysis knowledge area, Prioritize Requirements and Other Product Information (prioritisation in adaptive life cycles)

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0056)

Question 57 of 60

Business analysis · Task 5mediumone answer
Question 57. A power utility is running a predictive project to replace its meter-reading system, and the requirements baseline was approved two months ago. During build, the energy regulator's representative tells the business analyst that a mandatory reporting field must change format. How should the analyst handle this?

Pick one answer, then check.

Check the answer

Correct answer

  • AAssess the impact of the change and submit it through the agreed change control process

In a predictive life cycle the business analyst works within a baselined set of requirements and treats any change, including a mandatory one, as a change request supported by impact analysis. The mandate affects the likely decision, not the route to it. A candidate who updated the matrix directly reasoned that a regulatory change needs no approval, which confuses the certainty of the outcome with the process that records and assesses it.

Why, option by option - Question 57

  • A. In a predictive approach the baseline is protected by change control. The analyst's role is to analyse what the regulator's change touches, across requirements, design, tests and schedule, and to bring that analysis to the change control process for a decision, however certain the outcome seems.

  • B. This is the informal shortcut: because the change is mandatory, it feels safe to apply it directly. But altering a baselined requirement without change control loses the impact analysis and the approval record that a predictive project depends on.

  • C. That is the adaptive reflex in a predictive setting. This project has no iteration backlog; it has an approved baseline, and requirements enter or leave it through change control.

  • D. Implementing first and documenting later bypasses the approval that governs a baseline and leaves the change unassessed. Lessons learned records what the project learned, not what changed in the requirements.

Објаснување на македонски (explanation in Macedonian)

Во предиктивен пристап барањата се заштитени со основна линија и секоја промена, дури и задолжителна, оди преку контрола на промени со анализа на влијанието. Аналитичарот го проценува влијанието и го поднесува барањето за промена. Директна измена на traceability matrix, додавање во backlog или градење без одобрување ја заобиколуваат договорената постапка.

Where this sits in PMI

PMI Guide to Business Analysis, Traceability and Monitoring knowledge area (managing changes to requirements); Process Groups: A Practice Guide, Perform Integrated Change Control

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0057)

Question 58 of 60

Business analysis · Task 6easyone answer
Question 58. A pharmacy chain's user story reads: "As a pharmacist, I want a warning when two drugs on a prescription interact, so that I can contact the prescribing doctor." Which acceptance criterion is written best?

Pick one answer, then check.

Check the answer

Correct answer

  • BWhen two drugs on the prescription are listed as interacting, a warning naming both is shown before the prescription can be confirmed

Acceptance criteria must be specific, testable and tied to the requirement they belong to: a condition, an observable outcome and where in the flow it applies. Vague qualities, team activities and restatements of the story are the three typical failures. A candidate who chose option A may have valued the pharmacist's experience, but a criterion that cannot be judged consistently cannot decide acceptance.

Why, option by option - Question 58

  • A. "Quickly" and "easy to notice" cannot be tested without someone deciding what they mean. A criterion that two testers could judge differently is not an acceptance criterion yet.

  • B. It states the condition, the observable result and the point at which it must occur, so a tester can set up the case and see a pass or fail. It is specific, testable and tied directly to the story.

  • C. This describes an activity of the team, not a property of the product. Acceptance criteria say what the solution must do for the story to be accepted, not what work must be performed.

  • D. This restates the story at the same level of generality and points to an unstated requirement elsewhere. It adds no condition a tester could check.

Објаснување на македонски (explanation in Macedonian)

Acceptance criteria мора да бидат конкретни, проверливи и врзани за барањето: услов, видлив резултат и момент во текот на работа. Опцијата B го дава токму тоа. Нејасни квалитети како „брзо“, опис на активност на тимот или повторување на приказната не можат да се тестираат.

Where this sits in PMI

PMI Guide to Business Analysis, Analysis knowledge area (acceptance criteria, user stories); Agile Practice Guide, section on user stories and definition of done

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0058)

Question 59 of 60

Business analysis · Task 6mediummultiple answers
Question 59. A freight company's operations director asks the business analyst whether the new dispatch module is ready to be handed over. Which two conditions must be met before the analyst can confirm that it is? (Choose two)

Pick two answers, then check.

Check the answer

Correct answers

  • BEvery requirement in the traceability matrix links to a deliverable that has passed verification
  • EThe stakeholders who own the need have validated the working module against the acceptance criteria

Readiness for delivery is evidence-based: complete traceability to verified deliverables (nothing lost, everything built right) and validation by the owning stakeholders against agreed acceptance criteria (the right thing built). A team's own completion signal, a sponsor's deadline and a passing test suite are the three tempting substitutes for that evidence. A candidate who chose option A or D took the team's own completion signal as readiness without checking traceability coverage or stakeholder validation.

Why, option by option - Question 59

  • A. Finishing the planned work is the team's own completion signal. It shows neither that every requirement is traced to a verified deliverable nor that the stakeholders who own the need have accepted the module against the acceptance criteria.

  • B. The traceability matrix is the instrument for readiness: when every requirement has a covering deliverable and that deliverable has been verified, nothing has been dropped and nothing is unproven. A gap in the matrix is a gap in the product.

  • C. Urgency from the sponsor is a constraint on the schedule, not a condition of readiness. Delivering to a date with unmet criteria transfers the problem to the users and to operations.

  • D. Passing the team's own tests is verification of what the team chose to test. It says nothing about whether every requirement in the traceability matrix is covered, or whether the stakeholders who own the need have validated the result.

  • E. Validation confirms that the right thing was built, and it belongs to the people whose need the module serves. Their confirmation against the agreed criteria is the second half of readiness alongside a complete, verified traceability matrix.

Објаснување на македонски (explanation in Macedonian)

Подготвеноста за испорака се докажува со две работи: секое барање во traceability matrix е поврзано со верифицирана испорака, и засегнатите страни што ја поседуваат потребата го потврдиле модулот според acceptance criteria. Тоа што тимот ја завршил планираната работа, брзањето на спонзорот и поминатите тестови на тимот сами по себе не се докази.

Where this sits in PMI

PMI Guide to Business Analysis, Solution Evaluation and Traceability and Monitoring knowledge areas (evaluating readiness, traceability); Process Groups: A Practice Guide, Validate Scope

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0059)

Question 60 of 60

Business analysis · Task 6hardone answer
Question 60. A newspaper's new subscription system has passed every system and integration test, and each requirement in the traceability matrix shows a passing test. The project manager proposes to move to acceptance. The subscriptions desk staff, whose needs the requirements were written from, have not yet used the release candidate. What should the business analyst recommend?

Pick one answer, then check.

Check the answer

Correct answer

  • CHave the desk staff exercise the release candidate against the acceptance criteria before acceptance

Verification and validation are separate: a passing test suite and a fully traced matrix show that the product was built right, while validation with the stakeholders who own the need shows that the right product was built. Both are required before acceptance, and the second is missing. A candidate who chose option A treated a complete traceability matrix as proof of acceptance; a candidate who chose the sponsor's signature let formal authority stand in for the stakeholders' confirmation.

Why, option by option - Question 60

  • A. Verification proves the product was built as specified; it is complete here. But acceptance rests on validation, which asks whether the specified product meets the need, and that question has not been put to the people who hold the need.

  • B. More verification does not answer a validation question. The tests already pass; running them again with other data checks the same thing more thoroughly and still leaves the desk staff unheard.

  • C. Validation confirms that the solution meets the stakeholders' actual need, and it is done by or with those stakeholders against the agreed criteria. Until the desk staff have done that, the traceability matrix shows a verified product, not an accepted one.

  • D. The sponsor's signature is the formal act, but signing on test results alone substitutes authority for validation. The sponsor should sign after the owning stakeholders have confirmed the solution against the criteria, not instead of them.

Објаснување на македонски (explanation in Macedonian)

Верификацијата покажува дека производот е изграден како што е специфицирано, а validation дека е изградено вистинското. Тестовите и traceability matrix ја покриваат само верификацијата. Пред прифаќање, вработените на десктот чии потреби се основа на барањата треба да го проверат решението според acceptance criteria; потписот на спонзорот доаѓа потоа, не наместо тоа.

Where this sits in PMI

PMI Guide to Business Analysis, Solution Evaluation knowledge area (validation versus verification, acceptance); Process Groups: A Practice Guide, Validate Scope and Control Quality

Checked in two rounds by chapter volunteers; review by a certified board member is pending. Found a problem with this question? Write to us (capm-0060)

Progress is kept only on this device, in the browser - no sign-in, no cookies, no server. Clearing the browser’s data clears it too.

Original practice questions written and reviewed by chapter volunteers. They are not PMI exam questions, are not endorsed by PMI and are no substitute for PMI’s official materials; they count towards no education hours and no PDUs. The exam is in English; the questions here are too. “PMI”, “CAPM”, “PMP” and “PMBOK” are registered marks of Project Management Institute, Inc. The chapter runs no exams - apply at pmi.org.

The questions follow the 2023 CAPM® Examination Content Outline and the PMBOK® Guide - Seventh Edition, which PMI names for this exam. When PMI revises the outline, the questions are withdrawn until they are re-mapped.